Construction Progress Billing, Schedule of Values (SOV) & Retainage Draw Calculator
Enter up to five divisions and reconcile cumulative installed work, eligible stored materials and previous certificates against the current payment due.
Worksheet inputs
Results
Billing and cash- Scheduled contract total
- $150,000.00
- Completed and stored to date
- $99,500.00
- Installed work to date
- 59%
- Materials currently stored
- $11,000.00
- Retainage held to date
- $9,950.00
- Total earned less retainage
- $89,550.00
- Previous certificates
- $39,600.00
- Balance to finish plus retainage
- $60,450.00
- Flat retainage applies to cumulative installed work and eligible stored materials.
- Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.
Schedule of values to date
| Division | Scheduled | Installed prior | Installed now | Stored | Earned before holdback |
|---|---|---|---|---|---|
| Site and concrete | $65,000.00 | $32,500.00 | $19,500.00 | $0.00 | $52,000.00 |
| Mechanical | $45,000.00 | $9,000.00 | $13,500.00 | $7,500.00 | $30,000.00 |
| Electrical | $40,000.00 | $6,000.00 | $8,000.00 | $3,500.00 | $17,500.00 |
Frequently asked questions
Does this calculator generate AIA G702 or G703 documents?
Use it to reconcile the math behind a progress billing. Obtain the appropriate forms and instructions through your contract administrator.
Is current-period completion cumulative?
Enter only the percentage newly installed this period. Add it to prior installed completion to arrive at cumulative installed work. Stored materials are dollar amounts entered separately.
How do the two retainage step-down methods differ?
Once installed work reaches the threshold, the excess-only method keeps the original holdback on the first tranche and uses the lower rate for the balance. Re-rating applies the lower rate to all eligible cumulative value.
Construction Progress Billing, Schedule of Values (SOV) & Retainage Draw Calculator
- Scheduled contract total
- $150,000.00
- Completed and stored to date
- $99,500.00
- Installed work to date
- 59%
- Materials currently stored
- $11,000.00
- Retainage held to date
- $9,950.00
- Total earned less retainage
- $89,550.00
- Previous certificates
- $39,600.00
- Balance to finish plus retainage
- $60,450.00
Worksheet inputs
- Trade division · 1
- Site and concrete
- Scheduled value · 1
- 65000 $
- Previous complete · 1
- 50 %
- This period complete · 1
- 30 %
- Stored materials · 1
- 0 $
- Trade division · 2
- Mechanical
- Scheduled value · 2
- 45000 $
- Previous complete · 2
- 20 %
- This period complete · 2
- 30 %
- Stored materials · 2
- 7500 $
- Trade division · 3
- Electrical
- Scheduled value · 3
- 40000 $
- Previous complete · 3
- 15 %
- This period complete · 3
- 20 %
- Stored materials · 3
- 3500 $
- Original retainage rate
- 10 %
- Previous certificates for payment
- 39600 $
- Retainage method
- Flat retainage
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.