Five-division mixed-use progress billing

Roll up a mixed-use schedule across foundations, framing, roofing, MEP and finishes with three categories of stored material.

Worksheet inputs

Division 1
$
%
%
$
Division 2
$
%
%
$
Division 3
$
%
%
$
Division 4
$
%
%
$
Division 5
$
%
%
$
Retainage and prior certificates

The threshold uses installed value across the SOV. Leave unused divisions at zero.

%
$

Results

Billing and cash
Current payment due this draw$58,342.50
Scheduled contract total
$300,000.00
Completed and stored to date
$138,150.00
Installed work to date
38.72%
Materials currently stored
$22,000.00
Retainage held to date
$6,907.50
Total earned less retainage
$131,242.50
Previous certificates
$72,900.00
Balance to finish plus retainage
$168,757.50
Schedule of values and retainage held
Schedule of values and retainage heldContract sum. Earned less retainage $131,242.50. Retainage held $6,907.50. Work remaining $161,850.00Contract sum$300KEarned less retainageRetainage heldWork remaining
  • Flat retainage applies to cumulative installed work and eligible stored materials.
  • Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.

Schedule of values to date

DivisionScheduledInstalled priorInstalled nowStoredEarned before holdback
Foundations$54,000.00$37,800.00$16,200.00$0.00$54,000.00
Framing$86,000.00$25,800.00$17,200.00$8,000.00$51,000.00
Roofing$37,000.00$0.00$5,550.00$7,000.00$12,550.00
Mechanical and electrical$68,000.00$6,800.00$6,800.00$3,000.00$16,600.00
Finishes$55,000.00$0.00$0.00$4,000.00$4,000.00

How to use this example

The structure and roofing package advances while finishes remain stored. A single 5% rate applies to eligible cumulative value across the five lines.

Match the sum of the division amounts to the current approved contract total. Combine similar scope when you need additional detail outside the five-entry model.

Open calculator defaults

Frequently asked questions

Should I average the percentages of each division?

Use value-weighted installation. A large framing line contributes more to total installed progress than a smaller roofing line at the same percentage.

Can finished foundations stay in the SOV?

Yes. Keep completed divisions in the cumulative schedule at 100%, with zero new progress and zero stored amount if all material is installed.