Five-division mixed-use progress billing
Roll up a mixed-use schedule across foundations, framing, roofing, MEP and finishes with three categories of stored material.
Worksheet inputs
Results
Billing and cash- Scheduled contract total
- $300,000.00
- Completed and stored to date
- $138,150.00
- Installed work to date
- 38.72%
- Materials currently stored
- $22,000.00
- Retainage held to date
- $6,907.50
- Total earned less retainage
- $131,242.50
- Previous certificates
- $72,900.00
- Balance to finish plus retainage
- $168,757.50
- Flat retainage applies to cumulative installed work and eligible stored materials.
- Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.
Schedule of values to date
| Division | Scheduled | Installed prior | Installed now | Stored | Earned before holdback |
|---|---|---|---|---|---|
| Foundations | $54,000.00 | $37,800.00 | $16,200.00 | $0.00 | $54,000.00 |
| Framing | $86,000.00 | $25,800.00 | $17,200.00 | $8,000.00 | $51,000.00 |
| Roofing | $37,000.00 | $0.00 | $5,550.00 | $7,000.00 | $12,550.00 |
| Mechanical and electrical | $68,000.00 | $6,800.00 | $6,800.00 | $3,000.00 | $16,600.00 |
| Finishes | $55,000.00 | $0.00 | $0.00 | $4,000.00 | $4,000.00 |
How to use this example
The structure and roofing package advances while finishes remain stored. A single 5% rate applies to eligible cumulative value across the five lines.
Match the sum of the division amounts to the current approved contract total. Combine similar scope when you need additional detail outside the five-entry model.
Open calculator defaultsFrequently asked questions
Should I average the percentages of each division?
Use value-weighted installation. A large framing line contributes more to total installed progress than a smaller roofing line at the same percentage.
Can finished foundations stay in the SOV?
Yes. Keep completed divisions in the cumulative schedule at 100%, with zero new progress and zero stored amount if all material is installed.
Five-division mixed-use progress billing
- Scheduled contract total
- $300,000.00
- Completed and stored to date
- $138,150.00
- Installed work to date
- 38.72%
- Materials currently stored
- $22,000.00
- Retainage held to date
- $6,907.50
- Total earned less retainage
- $131,242.50
- Previous certificates
- $72,900.00
- Balance to finish plus retainage
- $168,757.50
Worksheet inputs
- Trade division · 1
- Foundations
- Scheduled value · 1
- 54000 $
- Previous complete · 1
- 70 %
- This period complete · 1
- 30 %
- Stored materials · 1
- 0 $
- Trade division · 2
- Framing
- Scheduled value · 2
- 86000 $
- Previous complete · 2
- 30 %
- This period complete · 2
- 20 %
- Stored materials · 2
- 8000 $
- Trade division · 3
- Roofing
- Scheduled value · 3
- 37000 $
- Previous complete · 3
- 0 %
- This period complete · 3
- 15 %
- Stored materials · 3
- 7000 $
- Trade division · 4
- Mechanical and electrical
- Scheduled value · 4
- 68000 $
- Previous complete · 4
- 10 %
- This period complete · 4
- 10 %
- Stored materials · 4
- 3000 $
- Trade division · 5
- Finishes
- Scheduled value · 5
- 55000 $
- Previous complete · 5
- 0 %
- This period complete · 5
- 0 %
- Stored materials · 5
- 4000 $
- Original retainage rate
- 5 %
- Previous certificates for payment
- 72900 $
- Retainage method
- Flat retainage
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.