Foundation and MEP second progress draw

Reconcile foundation and mechanical progress, current stored materials and a prior certificate against the second draw on a two-division SOV.

Worksheet inputs

Division 1
$
%
%
$
Division 2
$
%
%
$
Division 3
$
%
%
$
Division 4
$
%
%
$
Division 5
$
%
%
$
Retainage and prior certificates

The threshold uses installed value across the SOV. Leave unused divisions at zero.

%
$

Results

Billing and cash
Current payment due this draw$46,800.00
Scheduled contract total
$120,000.00
Completed and stored to date
$82,000.00
Installed work to date
63.33%
Materials currently stored
$6,000.00
Retainage held to date
$8,200.00
Total earned less retainage
$73,800.00
Previous certificates
$27,000.00
Balance to finish plus retainage
$46,200.00
Schedule of values and retainage held
Schedule of values and retainage heldContract sum. Earned less retainage $73,800.00. Retainage held $8,200.00. Work remaining $38,000.00Contract sum$120KEarned less retainageRetainage heldWork remaining
  • Flat retainage applies to cumulative installed work and eligible stored materials.
  • Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.

Schedule of values to date

DivisionScheduledInstalled priorInstalled nowStoredEarned before holdback
Foundations$80,000.00$32,000.00$24,000.00$4,000.00$60,000.00
Mechanical and electrical$40,000.00$10,000.00$10,000.00$2,000.00$22,000.00

How to use this example

Enter 30% newly installed foundations this period after 40% previously installed. The currently stored material amounts exclude items already put in place.

The previous certificate is entered as the cumulative amount already certified. Align that basis with the pay application register.

Open calculator defaults

Frequently asked questions

Can stored anchor hardware stay on the draw after installation?

Move its value out of stored inventory once installed and include the applicable installed value in the current progress amount.

What is the cleanest check on prior certificates?

Reconcile the cumulative certificates to the last approved application and include any approved adjustment on the same basis used in the current sheet.