Foundation and MEP second progress draw
Reconcile foundation and mechanical progress, current stored materials and a prior certificate against the second draw on a two-division SOV.
Worksheet inputs
Results
Billing and cash- Scheduled contract total
- $120,000.00
- Completed and stored to date
- $82,000.00
- Installed work to date
- 63.33%
- Materials currently stored
- $6,000.00
- Retainage held to date
- $8,200.00
- Total earned less retainage
- $73,800.00
- Previous certificates
- $27,000.00
- Balance to finish plus retainage
- $46,200.00
- Flat retainage applies to cumulative installed work and eligible stored materials.
- Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.
Schedule of values to date
| Division | Scheduled | Installed prior | Installed now | Stored | Earned before holdback |
|---|---|---|---|---|---|
| Foundations | $80,000.00 | $32,000.00 | $24,000.00 | $4,000.00 | $60,000.00 |
| Mechanical and electrical | $40,000.00 | $10,000.00 | $10,000.00 | $2,000.00 | $22,000.00 |
How to use this example
Enter 30% newly installed foundations this period after 40% previously installed. The currently stored material amounts exclude items already put in place.
The previous certificate is entered as the cumulative amount already certified. Align that basis with the pay application register.
Open calculator defaultsFrequently asked questions
Can stored anchor hardware stay on the draw after installation?
Move its value out of stored inventory once installed and include the applicable installed value in the current progress amount.
What is the cleanest check on prior certificates?
Reconcile the cumulative certificates to the last approved application and include any approved adjustment on the same basis used in the current sheet.
Foundation and MEP second progress draw
- Scheduled contract total
- $120,000.00
- Completed and stored to date
- $82,000.00
- Installed work to date
- 63.33%
- Materials currently stored
- $6,000.00
- Retainage held to date
- $8,200.00
- Total earned less retainage
- $73,800.00
- Previous certificates
- $27,000.00
- Balance to finish plus retainage
- $46,200.00
Worksheet inputs
- Trade division · 1
- Foundations
- Scheduled value · 1
- 80000 $
- Previous complete · 1
- 40 %
- This period complete · 1
- 30 %
- Stored materials · 1
- 4000 $
- Trade division · 2
- Mechanical and electrical
- Scheduled value · 2
- 40000 $
- Previous complete · 2
- 25 %
- This period complete · 2
- 25 %
- Stored materials · 2
- 2000 $
- Original retainage rate
- 10 %
- Previous certificates for payment
- 27000 $
- Retainage method
- Flat retainage
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.