Hospital fit-out with cumulative retainage re-rating
Estimate a hospital fit-out draw after an approved reduction applies the lower holdback rate to all cumulative eligible value.
Worksheet inputs
Results
Billing and cash- Scheduled contract total
- $250,000.00
- Completed and stored to date
- $160,000.00
- Installed work to date
- 60%
- Materials currently stored
- $10,000.00
- Retainage held to date
- $4,800.00
- Total earned less retainage
- $155,200.00
- Previous certificates
- $98,000.00
- Balance to finish plus retainage
- $94,800.00
- The installed-work threshold has been reached. The selected step-down method applies.
- Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.
Schedule of values to date
| Division | Scheduled | Installed prior | Installed now | Stored | Earned before holdback |
|---|---|---|---|---|---|
| Isolation rooms | $150,000.00 | $60,000.00 | $30,000.00 | $6,000.00 | $96,000.00 |
| Medical gas and controls | $100,000.00 | $35,000.00 | $25,000.00 | $4,000.00 | $64,000.00 |
How to use this example
The contract team has confirmed the example re-rates all eligible value once installed work reaches the trigger. Review what the step-down applies to before entering a lower rate.
Compare the re-rated draw against flat retainage to isolate the release component. Prior certificates stay at the amount previously certified.
Open calculator defaultsFrequently asked questions
Why can this draw exceed the value installed this month?
A cumulative re-rating can release some previously held retainage on top of the current work value. Reconcile the change as a separate adjustment in your billing records.
Should medical equipment on order count as stored materials?
Use eligible inventory documented for the draw under the signed terms. An equipment order by itself does not establish the value available for certification.
Hospital fit-out with cumulative retainage re-rating
- Scheduled contract total
- $250,000.00
- Completed and stored to date
- $160,000.00
- Installed work to date
- 60%
- Materials currently stored
- $10,000.00
- Retainage held to date
- $4,800.00
- Total earned less retainage
- $155,200.00
- Previous certificates
- $98,000.00
- Balance to finish plus retainage
- $94,800.00
Worksheet inputs
- Trade division · 1
- Isolation rooms
- Scheduled value · 1
- 150000 $
- Previous complete · 1
- 40 %
- This period complete · 1
- 20 %
- Stored materials · 1
- 6000 $
- Trade division · 2
- Medical gas and controls
- Scheduled value · 2
- 100000 $
- Previous complete · 2
- 35 %
- This period complete · 2
- 25 %
- Stored materials · 2
- 4000 $
- Original retainage rate
- 8 %
- Previous certificates for payment
- 98000 $
- Retainage method
- Re-rate all earned value
- Installed progress trigger
- 50 %
- Reduced retainage rate
- 3 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.