Punch-list completion and retainage release draw
Calculate a closeout draw with all work installed and retainage released, then reconcile it against previous certificates.
Worksheet inputs
Results
Billing and cash- Scheduled contract total
- $100,000.00
- Completed and stored to date
- $100,000.00
- Installed work to date
- 100%
- Materials currently stored
- $0.00
- Retainage held to date
- $0.00
- Total earned less retainage
- $100,000.00
- Previous certificates
- $87,000.00
- Balance to finish plus retainage
- $0.00
- Flat retainage applies to cumulative installed work and eligible stored materials.
- Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.
Schedule of values to date
| Division | Scheduled | Installed prior | Installed now | Stored | Earned before holdback |
|---|---|---|---|---|---|
| Interior construction | $66,000.00 | $62,700.00 | $3,300.00 | $0.00 | $66,000.00 |
| Finishes and punch work | $34,000.00 | $30,600.00 | $3,400.00 | $0.00 | $34,000.00 |
How to use this example
The work reaches 100% with all stored materials cleared. Zero current retainage represents a fully authorized release in this scenario.
Check closeout documents, approvals and actual release timing with the project team before treating the balance as collectible.
Open calculator defaultsFrequently asked questions
How can I see the effect of a partial closeout holdback?
Enter the approved remaining holdback as a percentage of cumulative eligible value or use a separate reconciliation when it is a fixed sum.
Is final payment equal to the last five or ten percent installed?
The request is cumulative and subtracts prior certificates. It may also include an approved release of retainage from earlier draws.
Punch-list completion and retainage release draw
- Scheduled contract total
- $100,000.00
- Completed and stored to date
- $100,000.00
- Installed work to date
- 100%
- Materials currently stored
- $0.00
- Retainage held to date
- $0.00
- Total earned less retainage
- $100,000.00
- Previous certificates
- $87,000.00
- Balance to finish plus retainage
- $0.00
Worksheet inputs
- Trade division · 1
- Interior construction
- Scheduled value · 1
- 66000 $
- Previous complete · 1
- 95 %
- This period complete · 1
- 5 %
- Stored materials · 1
- 0 $
- Trade division · 2
- Finishes and punch work
- Scheduled value · 2
- 34000 $
- Previous complete · 2
- 90 %
- This period complete · 2
- 10 %
- Stored materials · 2
- 0 $
- Original retainage rate
- 0 %
- Previous certificates for payment
- 87000 $
- Retainage method
- Flat retainage
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.