Punch-list completion and retainage release draw

Calculate a closeout draw with all work installed and retainage released, then reconcile it against previous certificates.

Worksheet inputs

Division 1
$
%
%
$
Division 2
$
%
%
$
Division 3
$
%
%
$
Division 4
$
%
%
$
Division 5
$
%
%
$
Retainage and prior certificates

The threshold uses installed value across the SOV. Leave unused divisions at zero.

%
$

Results

Billing and cash
Current payment due this draw$13,000.00
Scheduled contract total
$100,000.00
Completed and stored to date
$100,000.00
Installed work to date
100%
Materials currently stored
$0.00
Retainage held to date
$0.00
Total earned less retainage
$100,000.00
Previous certificates
$87,000.00
Balance to finish plus retainage
$0.00
Schedule of values and retainage held
Schedule of values and retainage heldContract sum. Earned less retainage $100,000.00. Retainage held $0.00. Work remaining $0.00Contract sum$100KEarned less retainageRetainage heldWork remaining
  • Flat retainage applies to cumulative installed work and eligible stored materials.
  • Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.

Schedule of values to date

DivisionScheduledInstalled priorInstalled nowStoredEarned before holdback
Interior construction$66,000.00$62,700.00$3,300.00$0.00$66,000.00
Finishes and punch work$34,000.00$30,600.00$3,400.00$0.00$34,000.00

How to use this example

The work reaches 100% with all stored materials cleared. Zero current retainage represents a fully authorized release in this scenario.

Check closeout documents, approvals and actual release timing with the project team before treating the balance as collectible.

Open calculator defaults

Frequently asked questions

How can I see the effect of a partial closeout holdback?

Enter the approved remaining holdback as a percentage of cumulative eligible value or use a separate reconciliation when it is a fixed sum.

Is final payment equal to the last five or ten percent installed?

The request is cumulative and subtracts prior certificates. It may also include an approved release of retainage from earlier draws.