School renovation excess-only retainage step-down
Model a school renovation draw where installed progress clears 50% and the lower holdback applies only to the eligible value above the threshold.
Worksheet inputs
Results
Billing and cash- Scheduled contract total
- $250,000.00
- Completed and stored to date
- $157,000.00
- Installed work to date
- 61.2%
- Materials currently stored
- $4,000.00
- Retainage held to date
- $14,100.00
- Total earned less retainage
- $142,900.00
- Previous certificates
- $96,000.00
- Balance to finish plus retainage
- $107,100.00
- The installed-work threshold has been reached. The selected step-down method applies.
- Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.
Schedule of values to date
| Division | Scheduled | Installed prior | Installed now | Stored | Earned before holdback |
|---|---|---|---|---|---|
| Classroom build-out | $120,000.00 | $66,000.00 | $18,000.00 | $0.00 | $84,000.00 |
| Mechanical upgrades | $80,000.00 | $28,000.00 | $16,000.00 | $4,000.00 | $48,000.00 |
| Life safety | $50,000.00 | $15,000.00 | $10,000.00 | $0.00 | $25,000.00 |
How to use this example
The work is valued across three divisions. The original rate still applies to the first 125,000 of eligible value. Apply the lower rate to the balance once installed progress qualifies.
Run the prior draw using the same threshold definition before comparing the cash effect of the step-down.
Open calculator defaultsFrequently asked questions
Does a 50% threshold mean half the schedule activities are finished?
This model uses installed value divided by total scheduled value. Check whether the agreement uses value, a milestone or an approval to trigger the change.
Does excess-only step-down release old retainage?
The original tranche stays at its original rate in this setting. The lower rate applies to the cumulative amount above the threshold once eligible.
School renovation excess-only retainage step-down
- Scheduled contract total
- $250,000.00
- Completed and stored to date
- $157,000.00
- Installed work to date
- 61.2%
- Materials currently stored
- $4,000.00
- Retainage held to date
- $14,100.00
- Total earned less retainage
- $142,900.00
- Previous certificates
- $96,000.00
- Balance to finish plus retainage
- $107,100.00
Worksheet inputs
- Trade division · 1
- Classroom build-out
- Scheduled value · 1
- 120000 $
- Previous complete · 1
- 55 %
- This period complete · 1
- 15 %
- Stored materials · 1
- 0 $
- Trade division · 2
- Mechanical upgrades
- Scheduled value · 2
- 80000 $
- Previous complete · 2
- 35 %
- This period complete · 2
- 20 %
- Stored materials · 2
- 4000 $
- Trade division · 3
- Life safety
- Scheduled value · 3
- 50000 $
- Previous complete · 3
- 30 %
- This period complete · 3
- 20 %
- Stored materials · 3
- 0 $
- Original retainage rate
- 10 %
- Previous certificates for payment
- 96000 $
- Retainage method
- Step down on excess
- Installed progress trigger
- 50 %
- Reduced retainage rate
- 5 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.