School renovation excess-only retainage step-down

Model a school renovation draw where installed progress clears 50% and the lower holdback applies only to the eligible value above the threshold.

Worksheet inputs

Division 1
$
%
%
$
Division 2
$
%
%
$
Division 3
$
%
%
$
Division 4
$
%
%
$
Division 5
$
%
%
$
Retainage and prior certificates

The threshold uses installed value across the SOV. Leave unused divisions at zero.

%
$
%
%

Results

Billing and cash
Current payment due this draw$46,900.00
Scheduled contract total
$250,000.00
Completed and stored to date
$157,000.00
Installed work to date
61.2%
Materials currently stored
$4,000.00
Retainage held to date
$14,100.00
Total earned less retainage
$142,900.00
Previous certificates
$96,000.00
Balance to finish plus retainage
$107,100.00
Schedule of values and retainage held
Schedule of values and retainage heldContract sum. Earned less retainage $142,900.00. Retainage held $14,100.00. Work remaining $93,000.00Contract sum$250KEarned less retainageRetainage heldWork remaining
  • The installed-work threshold has been reached. The selected step-down method applies.
  • Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.

Schedule of values to date

DivisionScheduledInstalled priorInstalled nowStoredEarned before holdback
Classroom build-out$120,000.00$66,000.00$18,000.00$0.00$84,000.00
Mechanical upgrades$80,000.00$28,000.00$16,000.00$4,000.00$48,000.00
Life safety$50,000.00$15,000.00$10,000.00$0.00$25,000.00

How to use this example

The work is valued across three divisions. The original rate still applies to the first 125,000 of eligible value. Apply the lower rate to the balance once installed progress qualifies.

Run the prior draw using the same threshold definition before comparing the cash effect of the step-down.

Open calculator defaults

Frequently asked questions

Does a 50% threshold mean half the schedule activities are finished?

This model uses installed value divided by total scheduled value. Check whether the agreement uses value, a milestone or an approval to trigger the change.

Does excess-only step-down release old retainage?

The original tranche stays at its original rate in this setting. The lower rate applies to the cumulative amount above the threshold once eligible.