Stored-inventory certificate reconciliation
Model a negative progress draw after stored inventory is removed from eligible billings and prior certificates exceed net earned value.
Worksheet inputs
Results
Billing and cash- Scheduled contract total
- $100,000.00
- Completed and stored to date
- $37,000.00
- Installed work to date
- 37%
- Materials currently stored
- $0.00
- Retainage held to date
- $3,700.00
- Total earned less retainage
- $33,300.00
- Previous certificates
- $40,000.00
- Balance to finish plus retainage
- $66,700.00
- Flat retainage applies to cumulative installed work and eligible stored materials.
- Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.
- Previous certificates exceed earned value after retainage. Reconcile the difference before requesting payment.
Schedule of values to date
| Division | Scheduled | Installed prior | Installed now | Stored | Earned before holdback |
|---|---|---|---|---|---|
| Roof replacement | $80,000.00 | $32,000.00 | $0.00 | $0.00 | $32,000.00 |
| Flashings and edge metal | $20,000.00 | $5,000.00 | $0.00 | $0.00 | $5,000.00 |
How to use this example
A previously included inventory amount is no longer eligible and has yet to be installed. Enter the revised stored amount and preserve the actual prior certificate total.
The signed current draw exposes the reconciliation difference. Review it with the certifier before proposing an accounting adjustment.
Open calculator defaultsFrequently asked questions
Why does the calculation show a negative draw?
The previous certificates exceed cumulative earned value after retainage. A negative number quantifies the difference for review.
What if a prior certificate is formally corrected?
Update the previous certificate total to reflect the approved correction. Keep the original and revised schedules for comparison.
Stored-inventory certificate reconciliation
- Scheduled contract total
- $100,000.00
- Completed and stored to date
- $37,000.00
- Installed work to date
- 37%
- Materials currently stored
- $0.00
- Retainage held to date
- $3,700.00
- Total earned less retainage
- $33,300.00
- Previous certificates
- $40,000.00
- Balance to finish plus retainage
- $66,700.00
Worksheet inputs
- Trade division · 1
- Roof replacement
- Scheduled value · 1
- 80000 $
- Previous complete · 1
- 40 %
- This period complete · 1
- 0 %
- Stored materials · 1
- 0 $
- Trade division · 2
- Flashings and edge metal
- Scheduled value · 2
- 20000 $
- Previous complete · 2
- 25 %
- This period complete · 2
- 0 %
- Stored materials · 2
- 0 $
- Original retainage rate
- 10 %
- Previous certificates for payment
- 40000 $
- Retainage method
- Flat retainage
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.