Stored switchgear below the installed-work trigger
Test a progress draw where stored switchgear raises completed-and-stored value above 50% but installed value stays below the step-down trigger.
Worksheet inputs
Results
Billing and cash- Scheduled contract total
- $200,000.00
- Completed and stored to date
- $110,000.00
- Installed work to date
- 30%
- Materials currently stored
- $50,000.00
- Retainage held to date
- $11,000.00
- Total earned less retainage
- $99,000.00
- Previous certificates
- $22,000.00
- Balance to finish plus retainage
- $101,000.00
- The installed-work threshold has yet to be reached. The original retainage rate still applies.
- Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.
Schedule of values to date
| Division | Scheduled | Installed prior | Installed now | Stored | Earned before holdback |
|---|---|---|---|---|---|
| Distribution labor | $100,000.00 | $10,000.00 | $20,000.00 | $0.00 | $30,000.00 |
| Switchgear package | $100,000.00 | $20,000.00 | $10,000.00 | $50,000.00 | $80,000.00 |
How to use this example
The stored equipment adds 50,000 of eligible value, while the installed percentage remains 30%. The original rate applies because this model keys the step-down to installed work.
Confirm ownership, storage location, protection and certificates required for stored equipment before submitting a draw.
Open calculator defaultsFrequently asked questions
Why does completed-and-stored exceed the percentage that triggers step-down?
Stored inventory increases eligible billings. This example tests the step-down on the installed portion of the schedule of values.
How should I record switchgear moved from storage to the jobsite?
Keep the value under eligible stored materials until installed, subject to the contract’s storage rules. Shift it to installed progress once installation counts on the draw.
Stored switchgear below the installed-work trigger
- Scheduled contract total
- $200,000.00
- Completed and stored to date
- $110,000.00
- Installed work to date
- 30%
- Materials currently stored
- $50,000.00
- Retainage held to date
- $11,000.00
- Total earned less retainage
- $99,000.00
- Previous certificates
- $22,000.00
- Balance to finish plus retainage
- $101,000.00
Worksheet inputs
- Trade division · 1
- Distribution labor
- Scheduled value · 1
- 100000 $
- Previous complete · 1
- 10 %
- This period complete · 1
- 20 %
- Stored materials · 1
- 0 $
- Trade division · 2
- Switchgear package
- Scheduled value · 2
- 100000 $
- Previous complete · 2
- 20 %
- This period complete · 2
- 10 %
- Stored materials · 2
- 50000 $
- Original retainage rate
- 10 %
- Previous certificates for payment
- 22000 $
- Retainage method
- Step down on excess
- Installed progress trigger
- 50 %
- Reduced retainage rate
- 5 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.