Stored switchgear below the installed-work trigger

Test a progress draw where stored switchgear raises completed-and-stored value above 50% but installed value stays below the step-down trigger.

Worksheet inputs

Division 1
$
%
%
$
Division 2
$
%
%
$
Division 3
$
%
%
$
Division 4
$
%
%
$
Division 5
$
%
%
$
Retainage and prior certificates

The threshold uses installed value across the SOV. Leave unused divisions at zero.

%
$
%
%

Results

Billing and cash
Current payment due this draw$77,000.00
Scheduled contract total
$200,000.00
Completed and stored to date
$110,000.00
Installed work to date
30%
Materials currently stored
$50,000.00
Retainage held to date
$11,000.00
Total earned less retainage
$99,000.00
Previous certificates
$22,000.00
Balance to finish plus retainage
$101,000.00
Schedule of values and retainage held
Schedule of values and retainage heldContract sum. Earned less retainage $99,000.00. Retainage held $11,000.00. Work remaining $90,000.00Contract sum$200KEarned less retainageRetainage heldWork remaining
  • The installed-work threshold has yet to be reached. The original retainage rate still applies.
  • Current-period completion is incremental. Remove materials from stored inventory as you install them. Enter previous certified amounts on the same basis as the current application.

Schedule of values to date

DivisionScheduledInstalled priorInstalled nowStoredEarned before holdback
Distribution labor$100,000.00$10,000.00$20,000.00$0.00$30,000.00
Switchgear package$100,000.00$20,000.00$10,000.00$50,000.00$80,000.00

How to use this example

The stored equipment adds 50,000 of eligible value, while the installed percentage remains 30%. The original rate applies because this model keys the step-down to installed work.

Confirm ownership, storage location, protection and certificates required for stored equipment before submitting a draw.

Open calculator defaults

Frequently asked questions

Why does completed-and-stored exceed the percentage that triggers step-down?

Stored inventory increases eligible billings. This example tests the step-down on the installed portion of the schedule of values.

How should I record switchgear moved from storage to the jobsite?

Keep the value under eligible stored materials until installed, subject to the contract’s storage rules. Shift it to installed progress once installation counts on the draw.