HVAC service van billing rate
Build a customer billing rate for a three-technician HVAC service crew with annual van costs and paid travel that reduces utilization.
Worksheet inputs
Results
Field operations- True loaded cost per paid hour
- $55.18/hr
- Break-even billable rate
- $100.17/hr
- Actual billable hours per tech
- 1,300 hr
- Direct cost per billable hour
- $84.89/hr
- Overhead per billable hour
- $15.28/hr
- Annual gross profit per tech
- $41,064.19
- Annual gross profit for crew
- $123,192.56
- Annual gross margin per tech or crew
- 27.12%
- Annual net profit for crew
- $63,598.16
- Enter the share of paid time you actually invoice after travel, holidays, rain days, unbilled callbacks and warranty work. Annual gross profit is revenue less direct labor cost. Annual net profit also deducts company overhead.
How to use this example
The van carries dispatch stock and spends part of the day traveling between service calls. Use the actual ratio of chargeable time to all paid time.
Use the crew gross profit figure to see the annual effect of a small change in utilization. Keep parts markup and labor rate policies separate.
Open calculator defaultsFrequently asked questions
Do travel hours count as revenue hours for HVAC service?
Count travel that customers actually pay for. When dispatch travel is bundled into a flat call fee, allocate those receipts on a consistent basis across jobs.
How do I price a van used by two technicians?
Allocate its annual cost between the technicians or model the crew as a combined cost and capacity estimate. Avoid entering the full van cost per person.
HVAC service van billing rate
- True loaded cost per paid hour
- $55.18/hr
- Break-even billable rate
- $100.17/hr
- Actual billable hours per tech
- 1,300 hr
- Direct cost per billable hour
- $84.89/hr
- Overhead per billable hour
- $15.28/hr
- Annual gross profit per tech
- $41,064.19
- Annual gross profit for crew
- $123,192.56
- Annual gross margin per tech or crew
- 27.12%
- Annual net profit for crew
- $63,598.16
Worksheet inputs
- Base hourly wage per tech
- 38 $
- Payroll taxes
- 9 %
- Workers’ compensation
- 5 %
- General liability on wages
- 2 %
- Technicians in crew
- 3
- Benefits
- 8400 $
- Truck and fuel
- 11000 $
- Tools and uniforms
- 2800 $
- Paid hours per tech per year
- 2000 hr
- Actual billable utilization
- 65 %
- Company overhead on billable cost
- 18 %
- Target net profit margin
- 14 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.