Four-person masonry crew billing rate

Calculate the average loaded rate for a masonry crew with equipment support, workers’ compensation and unpaid-to-customer rain days.

Worksheet inputs

Wage and payroll burden
A$
%
%
%
Annual cost per technician
A$
A$
A$
Utilization and target return
hr
%
Use invoiced hours ÷ paid hours. Include travel, callbacks, holidays and weather downtime when estimating the gap.
%
%

Results

Field operations
Recommended customer T&M rateA$107.15/hr
True loaded cost per paid hour
A$57.19/hr
Break-even billable rate
A$93.22/hr
Actual billable hours per tech
1,314 hr
Direct cost per billable hour
A$78.34/hr
Overhead per billable hour
A$14.88/hr
Annual gross profit per tech
A$37,861.52
Annual gross profit for crew
A$151,446.07
Annual gross margin per tech or crew
26.89%
Annual net profit for crew
A$73,214.71
From hourly wage to billable rate
From hourly wage to billable rateWage A$41.00. Payroll burden A$9.02. Benefits & gear A$7.17. Unbilled time A$21.15. Overhead A$14.88. Profit A$13.93. T&M rate A$107.15A$0A$53.6A$107.2WagePayroll burdenBenefits & gearUnbilled timeOverheadProfitT&M rate
  • Enter the share of paid time you actually invoice after travel, holidays, rain days, unbilled callbacks and warranty work. Annual gross profit is revenue less direct labor cost. Annual net profit also deducts company overhead.

How to use this example

The wage is a representative average for the modeled crew. Validate the mixture of mason and helper hours when applying the rate to an individual project.

Enter rain and late-material stoppages in utilization only when workers are paid. Use the annual tool amount for shared equipment assigned per technician.

Open calculator defaults

Frequently asked questions

How do I turn the technician rate into a four-person crew hour?

Multiply the modeled per-person rate by four when each person works the full chargeable hour at the same average input. Use separate mixes where the staffing changes by phase.

How does shared scaffold setup affect a masonry estimate?

Budget actual paid setup time. If the cost is recovered as a separate direct line on the job, keep it consistent with the time included in the labor billing basis.