Service plumber warranty and callback hours
Estimate a plumbing T&M rate when repeat visits, warranty work and diagnostic travel leave only part of paid hours billable.
Worksheet inputs
Results
Field operations- True loaded cost per paid hour
- $48.68/hr
- Break-even billable rate
- $102.39/hr
- Actual billable hours per tech
- 1,206.4 hr
- Direct cost per billable hour
- $83.93/hr
- Overhead per billable hour
- $18.46/hr
- Annual gross profit per tech
- $44,073.36
- Annual gross profit for crew
- $176,293.42
- Annual gross margin per tech or crew
- 30.33%
- Annual net profit for crew
- $87,193.77
- Enter the share of paid time you actually invoice after travel, holidays, rain days, unbilled callbacks and warranty work. Annual gross profit is revenue less direct labor cost. Annual net profit also deducts company overhead.
How to use this example
The crew pays technicians on warranty calls and missed appointments. Use the lower realized utilization to spread those hours across time actually invoiced.
Compare several months of dispatch data. A busy month can still have low utilization when repeat calls fill the schedule.
Open calculator defaultsFrequently asked questions
Where does an unpaid leak callback show up in the labor rate?
Keep the visit in paid hours and out of billed hours. The reduced utilization increases the cost that each invoiced hour must recover.
Where do return-trip fittings belong?
Track parts used on callbacks as materials or warranty expense consistent with your accounting. This example uses labor utilization to capture the time.
Service plumber warranty and callback hours
- True loaded cost per paid hour
- $48.68/hr
- Break-even billable rate
- $102.39/hr
- Actual billable hours per tech
- 1,206.4 hr
- Direct cost per billable hour
- $83.93/hr
- Overhead per billable hour
- $18.46/hr
- Annual gross profit per tech
- $44,073.36
- Annual gross profit for crew
- $176,293.42
- Annual gross margin per tech or crew
- 30.33%
- Annual net profit for crew
- $87,193.77
Worksheet inputs
- Base hourly wage per tech
- 34 $
- Payroll taxes
- 10 %
- Workers’ compensation
- 5 %
- General liability on wages
- 3 %
- Technicians in crew
- 4
- Benefits
- 7200 $
- Truck and fuel
- 9000 $
- Tools and uniforms
- 1600 $
- Paid hours per tech per year
- 2080 hr
- Actual billable utilization
- 58 %
- Company overhead on billable cost
- 22 %
- Target net profit margin
- 15 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.