Solo finish carpenter billing rate
Set a finish carpenter’s hourly charge using an owner wage equivalent, small tool costs and time spent quoting or sourcing material.
Worksheet inputs
Results
Field operations- True loaded cost per paid hour
- £40.82/hr
- Break-even billable rate
- £67.06/hr
- Actual billable hours per tech
- 1,260 hr
- Direct cost per billable hour
- £58.31/hr
- Overhead per billable hour
- £8.75/hr
- Annual gross profit per tech
- £29,568.80
- Annual gross profit for crew
- £29,568.80
- Annual gross margin per tech or crew
- 28.7%
- Annual net profit for crew
- £18,547.70
- Enter the share of paid time you actually invoice after travel, holidays, rain days, unbilled callbacks and warranty work. Annual gross profit is revenue less direct labor cost. Annual net profit also deducts company overhead.
How to use this example
The input treats the owner’s labor as a cost per paid hour. Time estimating, picking up trim profiles and visiting work in progress cuts invoice capacity.
Enter only the truck and tool costs recovered through the labor charge. Where a project pays separate delivery, avoid recovering the same expense twice.
Open calculator defaultsFrequently asked questions
Why enter an owner wage when I take draws?
A wage equivalent values the hours spent on site. It lets the rate distinguish compensation for the owner’s time from profit on the business.
Should I include workshop setup time in billed hours?
Include it if the client pays for it under the job’s labor agreement. Otherwise leave the time in paid hours and recover it through utilization.
Solo finish carpenter billing rate
- True loaded cost per paid hour
- £40.82/hr
- Break-even billable rate
- £67.06/hr
- Actual billable hours per tech
- 1,260 hr
- Direct cost per billable hour
- £58.31/hr
- Overhead per billable hour
- £8.75/hr
- Annual gross profit per tech
- £29,568.80
- Annual gross profit for crew
- £29,568.80
- Annual gross margin per tech or crew
- 28.7%
- Annual net profit for crew
- £18,547.70
Worksheet inputs
- Base hourly wage per tech
- 29 £
- Payroll taxes
- 12 %
- Workers’ compensation
- 2 %
- General liability on wages
- 3 %
- Technicians in crew
- 1
- Benefits
- 4000 £
- Truck and fuel
- 6000 £
- Tools and uniforms
- 2400 £
- Paid hours per tech per year
- 1800 hr
- Actual billable utilization
- 70 %
- Company overhead on billable cost
- 15 %
- Target net profit margin
- 18 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.