Construction Change Order Pricing, Tiered O&P & Schedule-Impact Calculator

Price added or removed scope from direct trade costs. Keep self-performed overhead and profit, subcontract fees and extended general conditions visible.

Worksheet inputs

Signed scope deltas

Use negative amounts for credits or removed scope.

$
$
$
$
$
Contractual overhead and profit
%
%
%
%
Schedule and risk adders
$
days
%

Results

Estimating
Itemized change order total$29,878.37
Self-performed direct delta
$12,950.00
Self-performed overhead
$1,295.00
Self-performed profit
$1,424.50
Subcontract quote delta
$11,200.00
Subcontract pass-through O&P
$840.00
Extended general conditions
$1,800.00
Bond and insurance adder
$368.87
Modeled net profit change
$1,844.50
Effective net margin on added scope
6.17%
Updated contract sum
$274,878.37
Change order cost and fee build-up
Change order cost and fee build-upSelf direct $12,950.00. Self O&P $2,719.50. Sub quote $11,200.00. Sub O&P $840.00. Delay $1,800.00. Bond / ins. $368.87. Change total $29,878.37$0$14.9K$29.9KSelf directSelf O&PSub quoteSub O&PDelayBond / ins.Change total
  • Stacked O&P applies profit to self-performed cost plus overhead. Additive O&P prices both percentages directly on cost. The subcontract fee uses its own rate, with the entered share allocated to overhead.
  • Extended general conditions enter at cost. The bond and insurance adder applies to the entire signed subtotal. Verify how your agreement treats credits, markups and time extensions.

Frequently asked questions

What is the difference between stacked and additive 10% O&P?

On 1,000 of self-performed cost, additive 10% overhead plus 10% profit adds 200. Stacking applies profit to 1,100 and adds 210 overall.

Where do I price a credit from the subcontractor?

Enter the quote delta as negative. This model applies the entered pass-through and bond rates to signed amounts. Check the agreement for a different credit markup policy.

What belongs in the daily general conditions rate?

Use the daily incremental cost of items that actually extend, such as superintendent time, site facilities or traffic control. Exclude costs already in direct line items.