Elevator shaft revision with stacked O&P

Price an elevator shaft revision with stacked self-performed overhead and profit, a specialist subcontract and three days of extended site costs.

Worksheet inputs

Signed scope deltas

Use negative amounts for credits or removed scope.

$
$
$
$
$
Contractual overhead and profit
%
%
%
%
Schedule and risk adders
$
days
%

Results

Estimating
Itemized change order total$52,217.00
Self-performed direct delta
$25,000.00
Self-performed overhead
$2,500.00
Self-performed profit
$2,750.00
Subcontract quote delta
$18,000.00
Subcontract pass-through O&P
$1,350.00
Extended general conditions
$2,100.00
Bond and insurance adder
$517.00
Modeled net profit change
$3,560.00
Effective net margin on added scope
6.82%
Updated contract sum
$472,217.00
Change order cost and fee build-up
Change order cost and fee build-upSelf direct $25,000.00. Self O&P $5,250.00. Sub quote $18,000.00. Sub O&P $1,350.00. Delay $2,100.00. Bond / ins. $517.00. Change total $52,217.00$0$26.1K$52.2KSelf directSelf O&PSub quoteSub O&PDelayBond / ins.Change total
  • Stacked O&P applies profit to self-performed cost plus overhead. Additive O&P prices both percentages directly on cost. The subcontract fee uses its own rate, with the entered share allocated to overhead.
  • Extended general conditions enter at cost. The bond and insurance adder applies to the entire signed subtotal. Verify how your agreement treats credits, markups and time extensions.

How to use this example

The revision adds reinforcing, formwork and rigging. Apply the self-performed method only to changes in your direct scope.

The elevator contractor’s revised quote carries a separate pass-through fee. Price the superintendent and retained site facilities over three added days.

Open calculator defaults

Frequently asked questions

Should the elevator vendor’s markup also get a full self-performed fee?

Use the subcontract treatment specified in the agreement. This example applies the subcontract rate to the vendor quote and reserves stacked O&P for self-performed cost.

Where do I put a temporary hoist needed only for the revision?

Put the incremental rental and mobilization in equipment. Keep it separate from the daily cost of retaining existing site facilities.