Fire alarm subcontract pass-through change
Model a change that is mostly a fire alarm subcontract quote, with separate self-performed labor, a handling fee and bond adjustment.
Worksheet inputs
Results
Estimating- Self-performed direct delta
- $3,500.00
- Self-performed overhead
- $350.00
- Self-performed profit
- $385.00
- Subcontract quote delta
- $38,000.00
- Subcontract pass-through O&P
- $3,040.00
- Extended general conditions
- $0.00
- Bond and insurance adder
- $498.03
- Modeled net profit change
- $2,361.00
- Effective net margin on added scope
- 5.16%
- Updated contract sum
- $555,773.03
- Stacked O&P applies profit to self-performed cost plus overhead. Additive O&P prices both percentages directly on cost. The subcontract fee uses its own rate, with the entered share allocated to overhead.
- Extended general conditions enter at cost. The bond and insurance adder applies to the entire signed subtotal. Verify how your agreement treats credits, markups and time extensions.
How to use this example
The subcontract includes programming and required testing. Carry only your own rough-in adjustments in the self-performed delta.
Part of the subcontract fee recovers coordination overhead. Use the modeled margin to see what contribution remains after that allocation.
Open calculator defaultsFrequently asked questions
What if the fire alarm quote includes its own testing overhead?
Treat the complete subcontract quote as the direct signed amount. Apply only the pass-through rate allowed on that quote by your agreement.
Can the bond adjustment exceed the margin contribution?
It can be larger as a dollar amount. The example treats the bond add-on as a passed-through cost and excludes it from modeled net profit.
Fire alarm subcontract pass-through change
- Self-performed direct delta
- $3,500.00
- Self-performed overhead
- $350.00
- Self-performed profit
- $385.00
- Subcontract quote delta
- $38,000.00
- Subcontract pass-through O&P
- $3,040.00
- Extended general conditions
- $0.00
- Bond and insurance adder
- $498.03
- Modeled net profit change
- $2,361.00
- Effective net margin on added scope
- 5.16%
- Updated contract sum
- $555,773.03
Worksheet inputs
- Original contract sum
- 510000 $
- Self-performed labor delta
- 2500 $
- Materials delta
- 1000 $
- Equipment delta
- 0 $
- Subcontract quote delta
- 38000 $
- Self-performed O&P method
- Stack overhead and profit
- Self-performed overhead
- 10 %
- Self-performed profit
- 10 %
- Subcontract pass-through O&P
- 8 %
- Overhead share of subcontract O&P
- 35 %
- Extended general conditions per day
- 0 $
- Extended days
- 0 days
- Bond and insurance adder
- 1.1 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.