Time-only extension and daily general conditions

Price a seven-day time extension with no direct scope change and a daily project general conditions cost.

Worksheet inputs

Signed scope deltas

Use negative amounts for credits or removed scope.

$
$
$
$
$
Contractual overhead and profit
%
%
%
%
Schedule and risk adders
$
days
%

Results

Estimating
Itemized change order total$5,950.00
Self-performed direct delta
$0.00
Self-performed overhead
$0.00
Self-performed profit
$0.00
Subcontract quote delta
$0.00
Subcontract pass-through O&P
$0.00
Extended general conditions
$5,950.00
Bond and insurance adder
$0.00
Modeled net profit change
$0.00
Effective net margin on added scope
0%
Updated contract sum
$87,950.00
Change order cost and fee build-up
Change order cost and fee build-upSelf direct $0.00. Self O&P $0.00. Sub quote $0.00. Sub O&P $0.00. Delay $5,950.00. Bond / ins. $0.00. Change total $5,950.00$0$3K$6KSelf directSelf O&PSub quoteSub O&PDelayBond / ins.Change total
  • Stacked O&P applies profit to self-performed cost plus overhead. Additive O&P prices both percentages directly on cost. The subcontract fee uses its own rate, with the entered share allocated to overhead.
  • Extended general conditions enter at cost. The bond and insurance adder applies to the entire signed subtotal. Verify how your agreement treats credits, markups and time extensions.

How to use this example

The owner’s access revision shifts the finish date without adding installed work. Retain the project-level supervision and facilities that extend with the schedule.

This scenario puts the daily rate into the change at cost. Confirm the allowed line items and duration against approved schedule records.

Open calculator defaults

Frequently asked questions

Should a non-critical access delay extend all site costs?

Calculate costs that actually continue or are re-incurred. Validate the effect on the project finish and resources with the updated schedule.

Why does this time-only change show zero net profit?

Only extended general conditions contribute to the total. In this model that daily amount is recovered at cost, with self-performed and subcontract profit set by the scope deltas.