Time-only extension and daily general conditions
Price a seven-day time extension with no direct scope change and a daily project general conditions cost.
Worksheet inputs
Results
Estimating- Self-performed direct delta
- $0.00
- Self-performed overhead
- $0.00
- Self-performed profit
- $0.00
- Subcontract quote delta
- $0.00
- Subcontract pass-through O&P
- $0.00
- Extended general conditions
- $5,950.00
- Bond and insurance adder
- $0.00
- Modeled net profit change
- $0.00
- Effective net margin on added scope
- 0%
- Updated contract sum
- $87,950.00
- Stacked O&P applies profit to self-performed cost plus overhead. Additive O&P prices both percentages directly on cost. The subcontract fee uses its own rate, with the entered share allocated to overhead.
- Extended general conditions enter at cost. The bond and insurance adder applies to the entire signed subtotal. Verify how your agreement treats credits, markups and time extensions.
How to use this example
The owner’s access revision shifts the finish date without adding installed work. Retain the project-level supervision and facilities that extend with the schedule.
This scenario puts the daily rate into the change at cost. Confirm the allowed line items and duration against approved schedule records.
Open calculator defaultsFrequently asked questions
Should a non-critical access delay extend all site costs?
Calculate costs that actually continue or are re-incurred. Validate the effect on the project finish and resources with the updated schedule.
Why does this time-only change show zero net profit?
Only extended general conditions contribute to the total. In this model that daily amount is recovered at cost, with self-performed and subcontract profit set by the scope deltas.
Time-only extension and daily general conditions
- Self-performed direct delta
- $0.00
- Self-performed overhead
- $0.00
- Self-performed profit
- $0.00
- Subcontract quote delta
- $0.00
- Subcontract pass-through O&P
- $0.00
- Extended general conditions
- $5,950.00
- Bond and insurance adder
- $0.00
- Modeled net profit change
- $0.00
- Effective net margin on added scope
- 0%
- Updated contract sum
- $87,950.00
Worksheet inputs
- Original contract sum
- 82000 $
- Self-performed labor delta
- 0 $
- Materials delta
- 0 $
- Equipment delta
- 0 $
- Subcontract quote delta
- 0 $
- Self-performed O&P method
- Add both rates to cost
- Self-performed overhead
- 10 %
- Self-performed profit
- 10 %
- Subcontract pass-through O&P
- 5 %
- Overhead share of subcontract O&P
- 50 %
- Extended general conditions per day
- 850 $
- Extended days
- 7 days
- Bond and insurance adder
- 0 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.