Hospital smoke barrier change with additive O&P

Compare additive self-performed fees, specialty trade quote handling and site extension costs for a hospital smoke barrier revision.

Worksheet inputs

Signed scope deltas

Use negative amounts for credits or removed scope.

$
$
$
$
$
Contractual overhead and profit
%
%
%
%
Schedule and risk adders
$
days
%

Results

Estimating
Itemized change order total$45,441.55
Self-performed direct delta
$15,000.00
Self-performed overhead
$1,500.00
Self-performed profit
$1,500.00
Subcontract quote delta
$23,400.00
Subcontract pass-through O&P
$1,170.00
Extended general conditions
$2,200.00
Bond and insurance adder
$671.55
Modeled net profit change
$2,085.00
Effective net margin on added scope
4.59%
Updated contract sum
$660,441.55
Change order cost and fee build-up
Change order cost and fee build-upSelf direct $15,000.00. Self O&P $3,000.00. Sub quote $23,400.00. Sub O&P $1,170.00. Delay $2,200.00. Bond / ins. $671.55. Change total $45,441.55$0$22.7K$45.4KSelf directSelf O&PSub quoteSub O&PDelayBond / ins.Change total
  • Stacked O&P applies profit to self-performed cost plus overhead. Additive O&P prices both percentages directly on cost. The subcontract fee uses its own rate, with the entered share allocated to overhead.
  • Extended general conditions enter at cost. The bond and insurance adder applies to the entire signed subtotal. Verify how your agreement treats credits, markups and time extensions.

How to use this example

The signed pricing basis in the scenario applies both self-performed rates directly to cost. Compare the stacked option to identify the dollar difference before filing the quote.

Include required facility access controls in the daily extension cost only when they continue because of the approved change.

Open calculator defaults

Frequently asked questions

How do I include negative pressure and infection-control setup?

Add incremental installation and equipment to direct costs. Continuing daily monitoring can sit in extended general conditions when it genuinely extends.

What happens to the fee if the hospital approves only part of the scope?

Revise the signed cost deltas first. Update the extension days independently if partial approval changes the critical path.