Walk-in cooler scope credit
Calculate a signed change order credit after deleting a walk-in cooler upgrade and reducing self-performed labor and subcontract work.
Worksheet inputs
Results
Estimating- Self-performed direct delta
- −$9,000.00
- Self-performed overhead
- −$720.00
- Self-performed profit
- −$540.00
- Subcontract quote delta
- −$3,400.00
- Subcontract pass-through O&P
- −$170.00
- Extended general conditions
- $0.00
- Bond and insurance adder
- $0.00
- Modeled net profit change
- −$625.00
- Effective net margin on added scope
- —
- Updated contract sum
- $131,170.00
- Stacked O&P applies profit to self-performed cost plus overhead. Additive O&P prices both percentages directly on cost. The subcontract fee uses its own rate, with the entered share allocated to overhead.
- Extended general conditions enter at cost. The bond and insurance adder applies to the entire signed subtotal. Verify how your agreement treats credits, markups and time extensions.
How to use this example
Negative values reflect removed work. The example credits the related percentage fees on the same signed base.
Review supplier restocking and cancellation charges. Enter saved costs net of unavoidable charges if those charges remain with the job.
Open calculator defaultsFrequently asked questions
Can a deleted cooler have a positive restocking fee?
Yes. Offset the expected material saving with the supplier’s restocking or freight charge if the contract allocates it to the revised scope.
Why is margin on added scope unavailable for a credit?
There is no positive selling amount to use as the margin denominator. Review the modeled profit change in dollars and the updated contract sum.
Walk-in cooler scope credit
- Self-performed direct delta
- −$9,000.00
- Self-performed overhead
- −$720.00
- Self-performed profit
- −$540.00
- Subcontract quote delta
- −$3,400.00
- Subcontract pass-through O&P
- −$170.00
- Extended general conditions
- $0.00
- Bond and insurance adder
- $0.00
- Modeled net profit change
- −$625.00
- Effective net margin on added scope
- —
- Updated contract sum
- $131,170.00
Worksheet inputs
- Original contract sum
- 145000 $
- Self-performed labor delta
- -1800 $
- Materials delta
- -7200 $
- Equipment delta
- 0 $
- Subcontract quote delta
- -3400 $
- Self-performed O&P method
- Add both rates to cost
- Self-performed overhead
- 8 %
- Self-performed profit
- 6 %
- Subcontract pass-through O&P
- 5 %
- Overhead share of subcontract O&P
- 50 %
- Extended general conditions per day
- 0 $
- Extended days
- 0 days
- Bond and insurance adder
- 0 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.