Winter concrete weather protection change

Price heat, protection, a specialty quote and six additional site days for a concrete pour moved into a colder weather window.

Worksheet inputs

Signed scope deltas

Use negative amounts for credits or removed scope.

$
$
$
$
$
Contractual overhead and profit
%
%
%
%
Schedule and risk adders
$
days
%

Results

Estimating
Itemized change order total$19,057.44
Self-performed direct delta
$8,100.00
Self-performed overhead
$972.00
Self-performed profit
$725.76
Subcontract quote delta
$5,100.00
Subcontract pass-through O&P
$306.00
Extended general conditions
$3,480.00
Bond and insurance adder
$373.68
Modeled net profit change
$848.16
Effective net margin on added scope
4.45%
Updated contract sum
$331,057.44
Change order cost and fee build-up
Change order cost and fee build-upSelf direct $8,100.00. Self O&P $1,697.76. Sub quote $5,100.00. Sub O&P $306.00. Delay $3,480.00. Bond / ins. $373.68. Change total $19,057.44$0$9.5K$19.1KSelf directSelf O&PSub quoteSub O&PDelayBond / ins.Change total
  • Stacked O&P applies profit to self-performed cost plus overhead. Additive O&P prices both percentages directly on cost. The subcontract fee uses its own rate, with the entered share allocated to overhead.
  • Extended general conditions enter at cost. The bond and insurance adder applies to the entire signed subtotal. Verify how your agreement treats credits, markups and time extensions.

How to use this example

Blankets, enclosures and added field labor go in direct deltas. Retained site support comes in separately for six modeled days.

Use the expected signed extension days. Verify whether to include the added insurance and bond rate on every element of the change.

Open calculator defaults

Frequently asked questions

Should I charge heater fuel as a daily site overhead item?

Assign it to direct equipment or material when only the changed pour needs it. The extension line should contain time-related costs that continue for the site.

How do I price uncertain freeze protection duration?

Compare short and long duration cases using separate rates and days. State which weather and access assumptions are included in the quote.