Materials handling charge reaches overhead cap
See how a high pass-through handling charge can cover the entire fixed overhead plan before any recovery is assigned to field labor.
Worksheet inputs
Results
Estimating- Monthly overhead burn
- $6,250.00
- Single rate on direct costs
- 5%
- Dual rate on materials and subs
- 6%
- Dual rate on field labor
- 0%
- Dual recovery per field hour
- $0.00/hr
- Materials and subs recovery
- $75,000.00
- Field labor recovery
- $0.00
- Annual sales for net profit target
- $1,693,548.39
- The materials and field-labor allocations recover the same annual overhead as the single rate. Break-even revenue adds total direct costs and fixed overhead.
- The materials allocation reaches the full fixed-overhead budget. Any additional materials markup would contribute beyond modeled overhead.
How to use this example
An 8% handling charge on the full supply budget would exceed 75,000 of fixed overhead. The calculation caps materials recovery at the budget and leaves no residual field allocation.
Lower the rate to see how the same fixed cost redistributes. Treat contribution beyond fixed overhead separately in the pricing model.
Open calculator defaultsFrequently asked questions
Why is the effective materials rate lower than the rate I entered?
The handling result hit the annual fixed-overhead cap. The effective rate divides the capped recovery by the materials and subcontract budget.
What if annual material sales are much lower than expected?
Update the direct materials budget across the full year. If the handling charge falls below fixed overhead, the residual moves onto field labor.
Materials handling charge reaches overhead cap
- Monthly overhead burn
- $6,250.00
- Single rate on direct costs
- 5%
- Dual rate on materials and subs
- 6%
- Dual rate on field labor
- 0%
- Dual recovery per field hour
- $0.00/hr
- Materials and subs recovery
- $75,000.00
- Field labor recovery
- $0.00
- Annual sales for net profit target
- $1,693,548.39
Worksheet inputs
- Fixed company overhead
- 75000 $
- Direct materials and subs
- 1250000 $
- Direct field labor
- 250000 $
- Projected field labor hours
- 5000 hr
- Materials and subs handling markup
- 8 %
- Target net profit margin
- 7 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.