Labor-heavy drywall overhead recovery

Recover company overhead from a large field payroll budget and a modest gypsum board and compound allowance.

Worksheet inputs

Annual budget
C$
Include office, admin, fleet, marketing and insurance that sit outside direct job costs.
C$
C$
hr
Recovery and profit
%
The field labor base absorbs the remaining fixed overhead.
%

Results

Estimating
Break-even annual revenueC$1,050,000.00
Monthly overhead burn
C$17,500.00
Single rate on direct costs
25%
Dual rate on materials and subs
8%
Dual rate on field labor
29.64%
Dual recovery per field hour
C$14.82/hr
Materials and subs recovery
C$14,400.00
Field labor recovery
C$195,600.00
Annual sales for net profit target
C$1,153,846.15
Annual overhead allocated by pricing method
Annual overhead allocated by pricing methodSingle rate. Materials & subs C$45,000.00. Field labor C$165,000.00. Dual rate. Materials & subs C$14,400.00. Field labor C$195,600.00Single rateC$210KDual rateC$210KMaterials & subsField labor
  • The materials and field-labor allocations recover the same annual overhead as the single rate. Break-even revenue adds total direct costs and fixed overhead.

How to use this example

Board and compound prices are passed through a light handling markup. The model recovers most office, fleet and insurance costs from the field labor base.

Budget hours from actual booked work. A change in the ratio of hanging to finishing crews can move total labor dollars at the same number of hours.

Open calculator defaults

Frequently asked questions

Can I use the field rate for piece-rate drywall installs?

Convert the planned scope to the same hours or direct labor dollar basis used in your budget. Track the outcome with whichever recovery base you actually quote.

Why does a materials purchasing change move the labor rate?

Higher handling recovery lowers the fixed overhead remaining for field labor. A drop in annual direct materials moves recovery back onto labor when overhead stays fixed.