Low-voltage integrator dual-rate budget
Model low-voltage overhead recovery when panels and cabling are a pass-through base and commissioning labor carries most company overhead.
Worksheet inputs
Results
Estimating- Monthly overhead burn
- $14,583.33
- Single rate on direct costs
- 25%
- Dual rate on materials and subs
- 10%
- Dual rate on field labor
- 47.5%
- Dual recovery per field hour
- $23.75/hr
- Materials and subs recovery
- $42,000.00
- Field labor recovery
- $133,000.00
- Annual sales for net profit target
- $983,146.07
- The materials and field-labor allocations recover the same annual overhead as the single rate. Break-even revenue adds total direct costs and fixed overhead.
How to use this example
The annual supply base includes purchased panels, cabling and specialist testing. Commissioning and installation hours are weighted in the direct payroll budget.
Use the dollar-per-field-hour output for labor estimates only if the field hours in your estimate match the budget definition.
Open calculator defaultsFrequently asked questions
Can shop programming hours use the field recovery rate?
Include them if they are both directly budgeted and part of the projected hours pool. Otherwise define a separate pricing base for that work.
How do equipment rebates affect the handling base?
Use the net cost basis you can reasonably budget. If purchase rebates are uncertain, test the material recovery using both gross and expected net prices.
Low-voltage integrator dual-rate budget
- Monthly overhead burn
- $14,583.33
- Single rate on direct costs
- 25%
- Dual rate on materials and subs
- 10%
- Dual rate on field labor
- 47.5%
- Dual recovery per field hour
- $23.75/hr
- Materials and subs recovery
- $42,000.00
- Field labor recovery
- $133,000.00
- Annual sales for net profit target
- $983,146.07
Worksheet inputs
- Fixed company overhead
- 175000 $
- Direct materials and subs
- 420000 $
- Direct field labor
- 280000 $
- Projected field labor hours
- 5600 hr
- Materials and subs handling markup
- 10 %
- Target net profit margin
- 11 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.