Low-voltage integrator dual-rate budget

Model low-voltage overhead recovery when panels and cabling are a pass-through base and commissioning labor carries most company overhead.

Worksheet inputs

Annual budget
$
Include office, admin, fleet, marketing and insurance that sit outside direct job costs.
$
$
hr
Recovery and profit
%
The field labor base absorbs the remaining fixed overhead.
%

Results

Estimating
Break-even annual revenue$875,000.00
Monthly overhead burn
$14,583.33
Single rate on direct costs
25%
Dual rate on materials and subs
10%
Dual rate on field labor
47.5%
Dual recovery per field hour
$23.75/hr
Materials and subs recovery
$42,000.00
Field labor recovery
$133,000.00
Annual sales for net profit target
$983,146.07
Annual overhead allocated by pricing method
Annual overhead allocated by pricing methodSingle rate. Materials & subs $105,000.00. Field labor $70,000.00. Dual rate. Materials & subs $42,000.00. Field labor $133,000.00Single rate$175KDual rate$175KMaterials & subsField labor
  • The materials and field-labor allocations recover the same annual overhead as the single rate. Break-even revenue adds total direct costs and fixed overhead.

How to use this example

The annual supply base includes purchased panels, cabling and specialist testing. Commissioning and installation hours are weighted in the direct payroll budget.

Use the dollar-per-field-hour output for labor estimates only if the field hours in your estimate match the budget definition.

Open calculator defaults

Frequently asked questions

Can shop programming hours use the field recovery rate?

Include them if they are both directly budgeted and part of the projected hours pool. Otherwise define a separate pricing base for that work.

How do equipment rebates affect the handling base?

Use the net cost basis you can reasonably budget. If purchase rebates are uncertain, test the material recovery using both gross and expected net prices.