Contractor Working Capital Float, Net-30/60 AR Lag & Mobilization Deposit Calculator

See how far your cash drops before invoices clear. Compare credit terms and deposits against the days you actually pay payroll and suppliers.

Worksheet inputs

Project and cash burn
$
$
days
%
%
Receipts and disbursements
days
days
%
days
days
%

Results

Billing and cash
Peak working capital required$118,800.00
Peak funding day
70 days
Minimum upfront deposit to stay neutral
65%
Days until cash stays nonnegative
165 days
Days with positive closing cash
60 days
Line-of-credit interest drag
$2,199.65
Total direct cash costs
$288,000.00
Final cash before interest
$72,000.00
Mobilization cash on day zero
$36,000.00
Retainage released
$18,000.00
Days through final cash event
195 days
Cumulative project cash position
Cumulative project cash positionCash before interest. Peak cash trough, day 70, −$118,800.00−$118.8K$0$72K098195Project dayCash before interestPeak cash trough · 70
  • Project costs and earned revenue accrue evenly over 30-day months. Costs post before same-day receipts. Billing credits the deposit proportionally and withholds retainage on gross earned value.
  • Payroll and vendor costs settle on separate cycles. Retainage releases after the final progress receipt or the entered release lag, whichever is later. Interest accrues on each negative day-end balance.

Month-by-month cash position

Projection dayCumulative closing cash
Day 0$36,000.00
Day 30−$33,840.00
Day 60−$103,680.00
Day 90−$97,020.00
Day 120−$90,360.00
Day 150−$22,500.00
Day 180$54,000.00
Final · day 195$72,000.00

Frequently asked questions

What does peak working capital required measure?

It is the largest cumulative cash shortfall before interest. The model checks the cash position after disbursements and again after receipts on each event day.

How is the mobilization deposit credited?

The full deposit starts in cash on day zero. Each progress payment deducts the proportional earned share of that deposit so the total receipts reconcile to the contract price.

Why might a higher deposit never keep the project cash-neutral?

A progress receipt can finish crediting the deposit while costs are still due or retainage remains held. The tool reports when no deposit within the available payable contract value covers the modeled shortfall.