Electrical fit-out with 15-day billing on Net 45
Compare biweekly-style progress billing on an electrical fit-out with Net 45 terms and a partial upfront deposit.
Worksheet inputs
Results
Billing and cash- Peak funding day
- 90 days
- Minimum upfront deposit to stay neutral
- 69.3%
- Days until cash stays nonnegative
- 120 days
- Days with positive closing cash
- 72 days
- Line-of-credit interest drag
- $923.76
- Total direct cash costs
- $192,000.00
- Final cash before interest
- $48,000.00
- Mobilization cash on day zero
- $30,000.00
- Retainage released
- $12,000.00
- Days through final cash event
- 150 days
- Project costs and earned revenue accrue evenly over 30-day months. Costs post before same-day receipts. Billing credits the deposit proportionally and withholds retainage on gross earned value.
- Payroll and vendor costs settle on separate cycles. Retainage releases after the final progress receipt or the entered release lag, whichever is later. Interest accrues on each negative day-end balance.
Month-by-month cash position
| Projection day | Cumulative closing cash |
|---|---|
| Day 0 | $30,000.00 |
| Day 30 | $6,106.67 |
| Day 60 | −$42,386.67 |
| Day 90 | −$57,880.00 |
| Day 120 | $3,000.00 |
| Final · day 150 | $48,000.00 |
How to use this example
The progress billing interval is 15 calendar days. Supplier checks fall every 45 days while payroll posts every 14 days.
The billing interval and payment lag are separate controls. Verify that the buyer actually accepts early draws before using their cash benefit.
Open calculator defaultsFrequently asked questions
Can faster invoices shorten the cash gap on Net 45?
Yes. Earlier invoice dates generally move receipts earlier while the 45-day lag stays fixed. Check the resulting trough against supplier due dates.
Does the supplier payment cadence equal supplier invoice terms?
The cadence models when disbursements occur from the project start. Use a separate dated schedule if invoices or supplier deposits arrive unevenly.
Electrical fit-out with 15-day billing on Net 45
- Peak funding day
- 90 days
- Minimum upfront deposit to stay neutral
- 69.3%
- Days until cash stays nonnegative
- 120 days
- Days with positive closing cash
- 72 days
- Line-of-credit interest drag
- $923.76
- Total direct cash costs
- $192,000.00
- Final cash before interest
- $48,000.00
- Mobilization cash on day zero
- $30,000.00
- Retainage released
- $12,000.00
- Days through final cash event
- 150 days
Worksheet inputs
- Contract price
- 240000 $
- Direct cost per 30-day month
- 64000 $
- Project duration
- 90 days
- Upfront mobilization deposit
- 12.5 %
- Retainage on gross billings
- 5 %
- Progress billing interval
- 15 days
- Client payment terms
- Net 45
- Retainage release after completion
- 60 days
- Payroll share of direct costs
- 40 %
- Payroll payment cadence
- 14 days
- Supplier payment cadence
- 45 days
- Line-of-credit APR
- 9.75 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.