Electrical fit-out with 15-day billing on Net 45

Compare biweekly-style progress billing on an electrical fit-out with Net 45 terms and a partial upfront deposit.

Worksheet inputs

Project and cash burn
$
$
days
%
%
Receipts and disbursements
days
days
%
days
days
%

Results

Billing and cash
Peak working capital required$90,880.00
Peak funding day
90 days
Minimum upfront deposit to stay neutral
69.3%
Days until cash stays nonnegative
120 days
Days with positive closing cash
72 days
Line-of-credit interest drag
$923.76
Total direct cash costs
$192,000.00
Final cash before interest
$48,000.00
Mobilization cash on day zero
$30,000.00
Retainage released
$12,000.00
Days through final cash event
150 days
Cumulative project cash position
Cumulative project cash positionCash before interest. Peak cash trough, day 90, −$90,880.00−$90.9K$0$48K075150Project dayCash before interestPeak cash trough · 90
  • Project costs and earned revenue accrue evenly over 30-day months. Costs post before same-day receipts. Billing credits the deposit proportionally and withholds retainage on gross earned value.
  • Payroll and vendor costs settle on separate cycles. Retainage releases after the final progress receipt or the entered release lag, whichever is later. Interest accrues on each negative day-end balance.

Month-by-month cash position

Projection dayCumulative closing cash
Day 0$30,000.00
Day 30$6,106.67
Day 60−$42,386.67
Day 90−$57,880.00
Day 120$3,000.00
Final · day 150$48,000.00

How to use this example

The progress billing interval is 15 calendar days. Supplier checks fall every 45 days while payroll posts every 14 days.

The billing interval and payment lag are separate controls. Verify that the buyer actually accepts early draws before using their cash benefit.

Open calculator defaults

Frequently asked questions

Can faster invoices shorten the cash gap on Net 45?

Yes. Earlier invoice dates generally move receipts earlier while the 45-day lag stays fixed. Check the resulting trough against supplier due dates.

Does the supplier payment cadence equal supplier invoice terms?

The cadence models when disbursements occur from the project start. Use a separate dated schedule if invoices or supplier deposits arrive unevenly.