Commercial roofing cash flow on Net 30

Project a roofing contractor’s funding gap with monthly billing, 14-day payroll, supplier payments, retainage and a 10% mobilization deposit.

Worksheet inputs

Project and cash burn
$
$
days
%
%
Receipts and disbursements
days
days
%
days
days
%

Results

Billing and cash
Peak working capital required$69,000.00
Peak funding day
60 days
Minimum upfront deposit to stay neutral
61.25%
Days until cash stays nonnegative
120 days
Days with positive closing cash
58 days
Line-of-credit interest drag
$732.82
Total direct cash costs
$135,000.00
Final cash before interest
$45,000.00
Mobilization cash on day zero
$18,000.00
Retainage released
$9,000.00
Days through final cash event
150 days
Cumulative project cash position
Cumulative project cash positionCash before interest. Peak cash trough, day 60, −$69,000.00−$69K$0$45K075150Project dayCash before interestPeak cash trough · 60
  • Project costs and earned revenue accrue evenly over 30-day months. Costs post before same-day receipts. Billing credits the deposit proportionally and withholds retainage on gross earned value.
  • Payroll and vendor costs settle on separate cycles. Retainage releases after the final progress receipt or the entered release lag, whichever is later. Interest accrues on each negative day-end balance.

Month-by-month cash position

Projection dayCumulative closing cash
Day 0$18,000.00
Day 30−$25,500.00
Day 60−$18,000.00
Day 90−$10,500.00
Day 120$36,000.00
Final · day 150$45,000.00

How to use this example

The first invoice is issued at day 30 and paid on day 60. Vendor and payroll cycles put cash out before those receipts arrive.

Use the plotted trough to size a project-level funding reserve. Compare Net 30 with Net 60 to see how much earlier payment matters.

Open calculator defaults

Frequently asked questions

Why does a roofing job with a deposit still go cash-negative?

The deposit may fall below accumulated supplier and wage payments before the first invoice clears. Later progress payments also credit the deposit proportionally.

Should the first roof-material payment be moved to day zero?

This sheet spreads costs over the project with a cadence. If a large prepaid shipment dominates, stress-test shorter cycles or build a dated cash schedule for that payment.