Commercial roofing cash flow on Net 30
Project a roofing contractor’s funding gap with monthly billing, 14-day payroll, supplier payments, retainage and a 10% mobilization deposit.
Worksheet inputs
Results
Billing and cash- Peak funding day
- 60 days
- Minimum upfront deposit to stay neutral
- 61.25%
- Days until cash stays nonnegative
- 120 days
- Days with positive closing cash
- 58 days
- Line-of-credit interest drag
- $732.82
- Total direct cash costs
- $135,000.00
- Final cash before interest
- $45,000.00
- Mobilization cash on day zero
- $18,000.00
- Retainage released
- $9,000.00
- Days through final cash event
- 150 days
- Project costs and earned revenue accrue evenly over 30-day months. Costs post before same-day receipts. Billing credits the deposit proportionally and withholds retainage on gross earned value.
- Payroll and vendor costs settle on separate cycles. Retainage releases after the final progress receipt or the entered release lag, whichever is later. Interest accrues on each negative day-end balance.
Month-by-month cash position
| Projection day | Cumulative closing cash |
|---|---|
| Day 0 | $18,000.00 |
| Day 30 | −$25,500.00 |
| Day 60 | −$18,000.00 |
| Day 90 | −$10,500.00 |
| Day 120 | $36,000.00 |
| Final · day 150 | $45,000.00 |
How to use this example
The first invoice is issued at day 30 and paid on day 60. Vendor and payroll cycles put cash out before those receipts arrive.
Use the plotted trough to size a project-level funding reserve. Compare Net 30 with Net 60 to see how much earlier payment matters.
Open calculator defaultsFrequently asked questions
Why does a roofing job with a deposit still go cash-negative?
The deposit may fall below accumulated supplier and wage payments before the first invoice clears. Later progress payments also credit the deposit proportionally.
Should the first roof-material payment be moved to day zero?
This sheet spreads costs over the project with a cadence. If a large prepaid shipment dominates, stress-test shorter cycles or build a dated cash schedule for that payment.
Commercial roofing cash flow on Net 30
- Peak funding day
- 60 days
- Minimum upfront deposit to stay neutral
- 61.25%
- Days until cash stays nonnegative
- 120 days
- Days with positive closing cash
- 58 days
- Line-of-credit interest drag
- $732.82
- Total direct cash costs
- $135,000.00
- Final cash before interest
- $45,000.00
- Mobilization cash on day zero
- $18,000.00
- Retainage released
- $9,000.00
- Days through final cash event
- 150 days
Worksheet inputs
- Contract price
- 180000 $
- Direct cost per 30-day month
- 45000 $
- Project duration
- 90 days
- Upfront mobilization deposit
- 10 %
- Retainage on gross billings
- 5 %
- Progress billing interval
- 30 days
- Client payment terms
- Net 30
- Retainage release after completion
- 60 days
- Payroll share of direct costs
- 50 %
- Payroll payment cadence
- 14 days
- Supplier payment cadence
- 30 days
- Line-of-credit APR
- 12 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.