Tenant refresh with a cash-neutral deposit
Estimate the deposit needed to cover a short tenant refresh with faster invoicing, Net 30 terms and no retained progress billings.
Worksheet inputs
Results
Billing and cash- Peak funding day
- —
- Minimum upfront deposit to stay neutral
- 44%
- Days until cash stays nonnegative
- 0 days
- Days with positive closing cash
- 90 days
- Line-of-credit interest drag
- $0.00
- Total direct cash costs
- $72,000.00
- Final cash before interest
- $48,000.00
- Mobilization cash on day zero
- $60,000.00
- Retainage released
- $0.00
- Days through final cash event
- 90 days
- Project costs and earned revenue accrue evenly over 30-day months. Costs post before same-day receipts. Billing credits the deposit proportionally and withholds retainage on gross earned value.
- Payroll and vendor costs settle on separate cycles. Retainage releases after the final progress receipt or the entered release lag, whichever is later. Interest accrues on each negative day-end balance.
Month-by-month cash position
| Projection day | Cumulative closing cash |
|---|---|
| Day 0 | $60,000.00 |
| Day 30 | $25,200.00 |
| Day 60 | $20,400.00 |
| Final · day 90 | $48,000.00 |
How to use this example
The owner’s example deposit covers materials, shorter payroll cycles and the early work waiting for certification. There is no modeled holdback.
Compare the entered 50% with the minimum upfront percentage calculated for the same schedule. The estimate still needs contingency for late receipts.
Open calculator defaultsFrequently asked questions
How can I see exactly when a smaller tenant deposit creates a gap?
Set the deposit to the smaller percentage and check the trough day and monthly cash table. The model includes outflows before same-day receipts.
Why could one delayed payment change the neutral percentage?
The planned costs keep posting while a late receipt stays outstanding. Test longer terms or separate uneven costs in a dated projection.
Tenant refresh with a cash-neutral deposit
- Peak funding day
- —
- Minimum upfront deposit to stay neutral
- 44%
- Days until cash stays nonnegative
- 0 days
- Days with positive closing cash
- 90 days
- Line-of-credit interest drag
- $0.00
- Total direct cash costs
- $72,000.00
- Final cash before interest
- $48,000.00
- Mobilization cash on day zero
- $60,000.00
- Retainage released
- $0.00
- Days through final cash event
- 90 days
Worksheet inputs
- Contract price
- 120000 $
- Direct cost per 30-day month
- 36000 $
- Project duration
- 60 days
- Upfront mobilization deposit
- 50 %
- Retainage on gross billings
- 0 %
- Progress billing interval
- 15 days
- Client payment terms
- Net 30
- Retainage release after completion
- 0 days
- Payroll share of direct costs
- 50 %
- Payroll payment cadence
- 14 days
- Supplier payment cadence
- 30 days
- Line-of-credit APR
- 8 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.