Contractor Bid Price, Markup vs. Gross Margin & Profit Erosion Calculator
Turn labor, materials, subcontractors and equipment into a customer price. See where the money goes, and how much profit is left if your markup falls short.
Worksheet inputs
Results
Estimating- Direct job costs
- $93,000.00
- Base bid
- $124,000.00
- Cost markup
- 33.33%
- Gross margin
- 25%
- Overhead recovered
- $14,880.00
- Net profit
- $16,120.00
- Net profit margin
- 13%
- Base bid for desired profit
- $116,250.00
- Bond pass-through
- $1,860.00
- Sales tax pass-through
- $0.00
- Shortfall to desired profit
- $0.00
- Gross margin and net profit use the base bid as the denominator. The bond applies to the base bid and sales tax applies to its entered taxable share. Both charges pass through outside modeled profit.
Markup and margin on the same costs
| Pricing rule | Base bid | Markup | Gross margin |
|---|---|---|---|
| 25% cost markup | $116,250.00 | 25% | 20% |
| 25% gross margin | $124,000.00 | 33.33% | 25% |
| Your pricing rule | $124,000.00 | 33.33% | 25% |
Frequently asked questions
Why does 25% markup give me a 20% gross margin?
On 100 of direct costs, a 25% markup produces a price of 125 and gross profit of 25. Gross margin divides that 25 by the selling price, giving 20%.
How do I quote for 25% gross margin?
Divide direct costs by 0.75. A 25% gross margin requires a 33⅓% markup on cost. The base bid excludes the tax and bond pass-throughs entered here.
Why can my net profit be negative on a bid with gross profit?
The gross profit pool must first cover company overhead. If overhead consumes more than that pool, the net margin is negative even though the base bid exceeds direct costs.
Contractor Bid Price, Markup vs. Gross Margin & Profit Erosion Calculator
- Direct job costs
- $93,000.00
- Base bid
- $124,000.00
- Cost markup
- 33.33%
- Gross margin
- 25%
- Overhead recovered
- $14,880.00
- Net profit
- $16,120.00
- Net profit margin
- 13%
- Base bid for desired profit
- $116,250.00
- Bond pass-through
- $1,860.00
- Sales tax pass-through
- $0.00
- Shortfall to desired profit
- $0.00
Worksheet inputs
- Materials
- 42000 $
- Field labor
- 26500 $
- Subcontractors
- 18000 $
- Equipment and permits
- 6500 $
- Solve bid from
- Target gross margin
- Target gross margin
- 25 %
- Overhead share of base bid
- 12 %
- Desired net profit margin
- 8 %
- Bond on base bid
- 1.5 %
- Sales tax rate
- 0 %
- Taxable share of base bid
- 100 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.