Cold-storage mechanical cost-markup bid
Price a cold-storage mechanical scope with a cost markup, separate insulation quote, equipment allowance and bond pass-through.
Worksheet inputs
Results
Estimating- Direct job costs
- $112,000.00
- Base bid
- $151,200.00
- Cost markup
- 35%
- Gross margin
- 25.93%
- Overhead recovered
- $19,656.00
- Net profit
- $19,544.00
- Net profit margin
- 12.93%
- Base bid for desired profit
- $149,333.33
- Bond pass-through
- $1,512.00
- Sales tax pass-through
- $0.00
- Shortfall to desired profit
- $0.00
- Gross margin and net profit use the base bid as the denominator. The bond applies to the base bid and sales tax applies to its entered taxable share. Both charges pass through outside modeled profit.
Markup and margin on the same costs
| Pricing rule | Base bid | Markup | Gross margin |
|---|---|---|---|
| 25% cost markup | $140,000.00 | 25% | 20% |
| 25% gross margin | $149,333.33 | 33.33% | 25% |
| Your pricing rule | $151,200.00 | 35% | 25.93% |
How to use this example
The subcontract covers insulation labor and material. Carry commissioning and pipe support installation in the field labor allowance if they sit with your own crew.
Review the delivery window for refrigeration equipment before locking the equipment and labor amounts. Long gaps can make temporary storage a direct cost.
Open calculator defaultsFrequently asked questions
How do I carry startup work from a manufacturer?
Enter a job-specific startup service quote under subcontractors or a direct allowance. Keep it distinct from the crew hours needed to assist commissioning.
Should a separately billed bond inflate gross margin?
In this model the priced bond passes through outside the base bid. Compare operating margins using the base selling price.
Cold-storage mechanical cost-markup bid
- Direct job costs
- $112,000.00
- Base bid
- $151,200.00
- Cost markup
- 35%
- Gross margin
- 25.93%
- Overhead recovered
- $19,656.00
- Net profit
- $19,544.00
- Net profit margin
- 12.93%
- Base bid for desired profit
- $149,333.33
- Bond pass-through
- $1,512.00
- Sales tax pass-through
- $0.00
- Shortfall to desired profit
- $0.00
Worksheet inputs
- Materials
- 57200 $
- Field labor
- 38000 $
- Subcontractors
- 14000 $
- Equipment and permits
- 2800 $
- Solve bid from
- Cost markup
- Markup on direct costs
- 35 %
- Overhead share of base bid
- 13 %
- Desired net profit margin
- 12 %
- Bond on base bid
- 1 %
- Sales tax rate
- 0 %
- Taxable share of base bid
- 100 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.