Curb and gutter bid with overhead erosion
See why a positive gross margin on municipal curb and gutter work can still miss overhead recovery and produce a negative net profit.
Worksheet inputs
Results
Estimating- Direct job costs
- $80,000.00
- Base bid
- $96,000.00
- Cost markup
- 20%
- Gross margin
- 16.67%
- Overhead recovered
- $18,240.00
- Net profit
- −$2,240.00
- Net profit margin
- −2.33%
- Base bid for desired profit
- $112,676.06
- Bond pass-through
- $0.00
- Sales tax pass-through
- $0.00
- Shortfall to desired profit
- $11,840.00
- Gross margin and net profit use the base bid as the denominator. The bond applies to the base bid and sales tax applies to its entered taxable share. Both charges pass through outside modeled profit.
Markup and margin on the same costs
| Pricing rule | Base bid | Markup | Gross margin |
|---|---|---|---|
| 25% cost markup | $100,000.00 | 25% | 20% |
| 25% gross margin | $106,666.67 | 33.33% | 25% |
| Your pricing rule | $96,000.00 | 20% | 16.67% |
How to use this example
The paving subcontract and mobilized formwork costs are direct. The company allocates office costs at 19% of the bid. The sample 20% markup cannot support that overhead share.
Compare the base bid for desired profit with the priced bid. Decide whether a tighter production plan or a higher selling price can close the gap.
Open calculator defaultsFrequently asked questions
Why do short concrete pours cost more per metre?
Truck minimums, cleanup and setup time are spread across fewer units. Rebuild the direct estimate at the actual number of pours before applying markup.
Where should I add a second mobilization for phased road closures?
Add the incremental field payroll, equipment transport and traffic-control quote to direct costs. Include only the share borne by this scope.
Curb and gutter bid with overhead erosion
- Direct job costs
- $80,000.00
- Base bid
- $96,000.00
- Cost markup
- 20%
- Gross margin
- 16.67%
- Overhead recovered
- $18,240.00
- Net profit
- −$2,240.00
- Net profit margin
- −2.33%
- Base bid for desired profit
- $112,676.06
- Bond pass-through
- $0.00
- Sales tax pass-through
- $0.00
- Shortfall to desired profit
- $11,840.00
Worksheet inputs
- Materials
- 33500 $
- Field labor
- 25500 $
- Subcontractors
- 9500 $
- Equipment and permits
- 11500 $
- Solve bid from
- Cost markup
- Markup on direct costs
- 20 %
- Overhead share of base bid
- 19 %
- Desired net profit margin
- 10 %
- Bond on base bid
- 0 %
- Sales tax rate
- 0 %
- Taxable share of base bid
- 100 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.