Curb and gutter bid with overhead erosion

See why a positive gross margin on municipal curb and gutter work can still miss overhead recovery and produce a negative net profit.

Worksheet inputs

Direct job costs
$
$
$
$
Pricing and profit
%
%
%
Bond and sales tax
%
%
%

Results

Estimating
Bid price including pass-throughs$96,000.00
Direct job costs
$80,000.00
Base bid
$96,000.00
Cost markup
20%
Gross margin
16.67%
Overhead recovered
$18,240.00
Net profit
−$2,240.00
Net profit margin
−2.33%
Base bid for desired profit
$112,676.06
Bond pass-through
$0.00
Sales tax pass-through
$0.00
Shortfall to desired profit
$11,840.00
From direct costs to the customer bid
From direct costs to the customer bidDirect cost $80,000.00. Overhead $18,240.00. Net profit −$2,240.00. Bond $0.00. Sales tax $0.00. Bid price $96,000.00$0$49.1K$98.2KDirect costOverheadNet profitBondSales taxBid price
  • Gross margin and net profit use the base bid as the denominator. The bond applies to the base bid and sales tax applies to its entered taxable share. Both charges pass through outside modeled profit.

Markup and margin on the same costs

Pricing ruleBase bidMarkupGross margin
25% cost markup$100,000.0025%20%
25% gross margin$106,666.6733.33%25%
Your pricing rule$96,000.0020%16.67%

How to use this example

The paving subcontract and mobilized formwork costs are direct. The company allocates office costs at 19% of the bid. The sample 20% markup cannot support that overhead share.

Compare the base bid for desired profit with the priced bid. Decide whether a tighter production plan or a higher selling price can close the gap.

Open calculator defaults

Frequently asked questions

Why do short concrete pours cost more per metre?

Truck minimums, cleanup and setup time are spread across fewer units. Rebuild the direct estimate at the actual number of pours before applying markup.

Where should I add a second mobilization for phased road closures?

Add the incremental field payroll, equipment transport and traffic-control quote to direct costs. Include only the share borne by this scope.