Occupied office painting bid and taxable share

Estimate a phased office repaint with weekend labor, equipment and an illustrative sales tax share applied to the base bid.

Worksheet inputs

Direct job costs
$
$
$
$
Pricing and profit
%
%
%
Bond and sales tax
%
%
%

Results

Estimating
Bid price including pass-throughs$25,460.00
Direct job costs
$17,000.00
Base bid
$25,000.00
Cost markup
47.06%
Gross margin
32%
Overhead recovered
$4,500.00
Net profit
$3,500.00
Net profit margin
14%
Base bid for desired profit
$25,000.00
Bond pass-through
$0.00
Sales tax pass-through
$460.00
Shortfall to desired profit
$0.00
From direct costs to the customer bid
From direct costs to the customer bidDirect cost $17,000.00. Overhead $4,500.00. Net profit $3,500.00. Bond $0.00. Sales tax $460.00. Bid price $25,460.00$0$12.7K$25.5KDirect costOverheadNet profitBondSales taxBid price
  • Gross margin and net profit use the base bid as the denominator. The bond applies to the base bid and sales tax applies to its entered taxable share. Both charges pass through outside modeled profit.

Markup and margin on the same costs

Pricing ruleBase bidMarkupGross margin
25% cost markup$21,250.0025%20%
25% gross margin$22,666.6733.33%25%
Your pricing rule$25,000.0047.06%32%

How to use this example

Field labor reflects weekend access and return visits for occupied suites. Equipment includes the mobile scaffold and surface protection supplies assigned to the job.

The taxable share is a sample input. Replace it with the amount supported by the quote and applicable tax treatment.

Open calculator defaults

Frequently asked questions

Why does a phased office repaint need extra labor?

Crews may move protection, restore furniture access and repeat setup across suites. Estimate these activities for each phase before setting the sales price.

Can I test a lower off-hours labor premium?

Change field labor to reflect the revised shift agreement. Compare the new base bid and net profit before proposing the access change.