Occupied office painting bid and taxable share
Estimate a phased office repaint with weekend labor, equipment and an illustrative sales tax share applied to the base bid.
Worksheet inputs
Results
Estimating- Direct job costs
- $17,000.00
- Base bid
- $25,000.00
- Cost markup
- 47.06%
- Gross margin
- 32%
- Overhead recovered
- $4,500.00
- Net profit
- $3,500.00
- Net profit margin
- 14%
- Base bid for desired profit
- $25,000.00
- Bond pass-through
- $0.00
- Sales tax pass-through
- $460.00
- Shortfall to desired profit
- $0.00
- Gross margin and net profit use the base bid as the denominator. The bond applies to the base bid and sales tax applies to its entered taxable share. Both charges pass through outside modeled profit.
Markup and margin on the same costs
| Pricing rule | Base bid | Markup | Gross margin |
|---|---|---|---|
| 25% cost markup | $21,250.00 | 25% | 20% |
| 25% gross margin | $22,666.67 | 33.33% | 25% |
| Your pricing rule | $25,000.00 | 47.06% | 32% |
How to use this example
Field labor reflects weekend access and return visits for occupied suites. Equipment includes the mobile scaffold and surface protection supplies assigned to the job.
The taxable share is a sample input. Replace it with the amount supported by the quote and applicable tax treatment.
Open calculator defaultsFrequently asked questions
Why does a phased office repaint need extra labor?
Crews may move protection, restore furniture access and repeat setup across suites. Estimate these activities for each phase before setting the sales price.
Can I test a lower off-hours labor premium?
Change field labor to reflect the revised shift agreement. Compare the new base bid and net profit before proposing the access change.
Occupied office painting bid and taxable share
- Direct job costs
- $17,000.00
- Base bid
- $25,000.00
- Cost markup
- 47.06%
- Gross margin
- 32%
- Overhead recovered
- $4,500.00
- Net profit
- $3,500.00
- Net profit margin
- 14%
- Base bid for desired profit
- $25,000.00
- Bond pass-through
- $0.00
- Sales tax pass-through
- $460.00
- Shortfall to desired profit
- $0.00
Worksheet inputs
- Materials
- 5400 $
- Field labor
- 9500 $
- Subcontractors
- 650 $
- Equipment and permits
- 1450 $
- Solve bid from
- Target gross margin
- Target gross margin
- 32 %
- Overhead share of base bid
- 18 %
- Desired net profit margin
- 14 %
- Bond on base bid
- 0 %
- Sales tax rate
- 8 %
- Taxable share of base bid
- 23 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.