Standing-seam roofing bid at 25% markup
Compare cost markup with gross margin on a standing-seam roof replacement with field labor, a disposal subcontract and equipment rental.
Worksheet inputs
Results
Estimating- Direct job costs
- $47,500.00
- Base bid
- $59,375.00
- Cost markup
- 25%
- Gross margin
- 20%
- Overhead recovered
- $8,906.25
- Net profit
- $2,968.75
- Net profit margin
- 5%
- Base bid for desired profit
- $62,500.00
- Bond pass-through
- $0.00
- Sales tax pass-through
- $0.00
- Shortfall to desired profit
- $2,375.00
- Gross margin and net profit use the base bid as the denominator. The bond applies to the base bid and sales tax applies to its entered taxable share. Both charges pass through outside modeled profit.
Markup and margin on the same costs
| Pricing rule | Base bid | Markup | Gross margin |
|---|---|---|---|
| 25% cost markup | $59,375.00 | 25% | 20% |
| 25% gross margin | $63,333.33 | 33.33% | 25% |
| Your pricing rule | $59,375.00 | 25% | 20% |
How to use this example
Metal panels, clips and flashings are under materials. The dumpster and tear-off support quote is a direct subcontract. Use the equipment line for the lift and its delivery.
The 25% markup yields 20% gross margin. After the 15% overhead allocation, only 5% of the base bid remains as net profit.
Open calculator defaultsFrequently asked questions
Which costs change if rooftop staging takes another day?
Add the extended lift and any extra crew or traffic-control costs to the appropriate direct lines. Check whether the original rental period covers the delay.
How can I account for damaged decking after tear-off?
Price an expected quantity at the installed direct unit cost as a scenario. Keep the final repair quantity and pricing process tied to measured conditions.
Standing-seam roofing bid at 25% markup
- Direct job costs
- $47,500.00
- Base bid
- $59,375.00
- Cost markup
- 25%
- Gross margin
- 20%
- Overhead recovered
- $8,906.25
- Net profit
- $2,968.75
- Net profit margin
- 5%
- Base bid for desired profit
- $62,500.00
- Bond pass-through
- $0.00
- Sales tax pass-through
- $0.00
- Shortfall to desired profit
- $2,375.00
Worksheet inputs
- Materials
- 22500 $
- Field labor
- 17250 $
- Subcontractors
- 4500 $
- Equipment and permits
- 3250 $
- Solve bid from
- Cost markup
- Markup on direct costs
- 25 %
- Overhead share of base bid
- 15 %
- Desired net profit margin
- 9 %
- Bond on base bid
- 0 %
- Sales tax rate
- 0 %
- Taxable share of base bid
- 100 %
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.