Crew Production Rate, Man-Hours, Duration & Overtime Compression Calculator
Estimate the shifts needed to finish a takeoff. Compare extra hours and their productivity loss with the labor cost and calendar days saved.
Worksheet inputs
Results
Field operations- Baseline man-hours
- 492.31 hr
- Planned man-hours including overtime
- 517.74 hr
- Overtime man-hours
- 101.74 hr
- Regular workdays
- 16 days
- Planned elapsed calendar days
- 17 days
- Planned elapsed calendar weeks
- 2.43 wk
- Calendar days saved
- 5 days
- Regular labor cost
- $18,707.69
- Planned labor cost
- $21,607.38
- Labor cost increase
- $2,899.69
- Calendar buffer to target
- 3 days
- Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.
Regular and accelerated schedules
| Schedule | Workdays | Calendar days | Man-hours | Overtime hours | Labor cost |
|---|---|---|---|---|---|
| Regular | 16 | 22 | 492.31 hr | 0 hr | $18,707.69 |
| Accelerated | 13 | 17 | 517.74 hr | 101.74 hr | $21,607.38 |
Frequently asked questions
When should I use units per crew-day?
Use that basis when production history is measured as a whole crew’s output per regular shift. Enter the crew size and regular hours that produced the historical rate.
How does overtime productivity loss affect a shift?
Two overtime hours at 25% efficiency loss deliver the modeled output of 1.5 regular hours. Payroll still counts the actual hours at the entered overtime multiplier.
Why can a small scope reduction remove several calendar days?
The model counts scheduled shifts and intervening days off. Finishing on the last shift of a workweek can avoid the next shift and its preceding days off.
Crew Production Rate, Man-Hours, Duration & Overtime Compression Calculator
- Baseline man-hours
- 492.31 hr
- Planned man-hours including overtime
- 517.74 hr
- Overtime man-hours
- 101.74 hr
- Regular workdays
- 16 days
- Planned elapsed calendar days
- 17 days
- Planned elapsed calendar weeks
- 2.43 wk
- Calendar days saved
- 5 days
- Regular labor cost
- $18,707.69
- Planned labor cost
- $21,607.38
- Labor cost increase
- $2,899.69
- Calendar buffer to target
- 3 days
Worksheet inputs
- Takeoff measurement
- Area
- Total takeoff quantity
- 12800 ft²
- Production rate basis
- Per man-hour
- Baseline production rate
- 26 ft²/man-hr
- Crew size
- 4
- Regular hours per workday
- 8 hr
- Scheduled workdays per week
- 5 days
- Extra overtime per workday
- 2 hr
- Overtime efficiency loss
- 25 %
- Regular hourly labor cost
- 38 $
- Overtime wage multiplier
- 1.5 ×
- Target elapsed calendar days
- 20 days
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.