Crew Production Rate, Man-Hours, Duration & Overtime Compression Calculator

Estimate the shifts needed to finish a takeoff. Compare extra hours and their productivity loss with the labor cost and calendar days saved.

Worksheet inputs

Scope and baseline production
ft²
ft²/man-hr
hr
days
Overtime, wage and target
hr
%
$
×
days
Use zero to leave the target unset.

Results

Field operations
Workdays on accelerated schedule13 days
Baseline man-hours
492.31 hr
Planned man-hours including overtime
517.74 hr
Overtime man-hours
101.74 hr
Regular workdays
16 days
Planned elapsed calendar days
17 days
Planned elapsed calendar weeks
2.43 wk
Calendar days saved
5 days
Regular labor cost
$18,707.69
Planned labor cost
$21,607.38
Labor cost increase
$2,899.69
Calendar buffer to target
3 days
Schedule and labor cost at each pace
Schedule and labor cost at each paceElapsed calendar days. Regular 22 days. Accelerated 17 days. Labor cost. Regular $18,707.69. Accelerated $21,607.38Elapsed calendar days22 days17 daysLabor cost$18,707.69$21,607.38RegularAccelerated
  • Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.

Regular and accelerated schedules

ScheduleWorkdaysCalendar daysMan-hoursOvertime hoursLabor cost
Regular1622492.31 hr0 hr$18,707.69
Accelerated1317517.74 hr101.74 hr$21,607.38

Frequently asked questions

When should I use units per crew-day?

Use that basis when production history is measured as a whole crew’s output per regular shift. Enter the crew size and regular hours that produced the historical rate.

How does overtime productivity loss affect a shift?

Two overtime hours at 25% efficiency loss deliver the modeled output of 1.5 regular hours. Payroll still counts the actual hours at the entered overtime multiplier.

Why can a small scope reduction remove several calendar days?

The model counts scheduled shifts and intervening days off. Finishing on the last shift of a workweek can avoid the next shift and its preceding days off.