Concrete layout with no overtime output

Stress-test a four-day workweek where paid overtime contributes no additional layout production and increases labor costs.

Worksheet inputs

Scope and baseline production
ft
ft/man-hr
hr
days
Overtime, wage and target
hr
%
$
×
days
Use zero to leave the target unset.

Results

Field operations
Workdays on accelerated schedule4 days
Baseline man-hours
120 hr
Planned man-hours including overtime
138 hr
Overtime man-hours
18 hr
Regular workdays
4 days
Planned elapsed calendar days
4 days
Planned elapsed calendar weeks
0.57 wk
Calendar days saved
0 days
Regular labor cost
$5,400.00
Planned labor cost
$6,615.00
Labor cost increase
$1,215.00
Calendar buffer to target
2 days
Schedule and labor cost at each pace
Schedule and labor cost at each paceElapsed calendar days. Regular 4 days. Accelerated 4 days. Labor cost. Regular $5,400.00. Accelerated $6,615.00Elapsed calendar days4 days4 daysLabor cost$5,400.00$6,615.00RegularAccelerated
  • Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.

Regular and accelerated schedules

ScheduleWorkdaysCalendar daysMan-hoursOvertime hoursLabor cost
Regular44120 hr0 hr$5,400.00
Accelerated44138 hr18 hr$6,615.00

How to use this example

Use total efficiency loss as a planning stress test for extra time blocked by work windows or site constraints. Scheduled overtime still incurs pay when it is used.

The regular and accelerated completion dates are the same. Compare the labor cost before committing to extra shifts or hours.

Open calculator defaults

Frequently asked questions

What does 100% overtime efficiency loss represent here?

The entered overtime accrues labor cost and contributes zero modeled output. Use it to stress-test paid time when field progress cannot continue.

Why does the last shift skip scheduled overtime?

The model stops paying crew hours once the work is complete. It incurs overtime on prior full shifts even if the entered efficiency yields no progress.