Concrete layout with no overtime output
Stress-test a four-day workweek where paid overtime contributes no additional layout production and increases labor costs.
Worksheet inputs
Results
Field operations- Baseline man-hours
- 120 hr
- Planned man-hours including overtime
- 138 hr
- Overtime man-hours
- 18 hr
- Regular workdays
- 4 days
- Planned elapsed calendar days
- 4 days
- Planned elapsed calendar weeks
- 0.57 wk
- Calendar days saved
- 0 days
- Regular labor cost
- $5,400.00
- Planned labor cost
- $6,615.00
- Labor cost increase
- $1,215.00
- Calendar buffer to target
- 2 days
- Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.
Regular and accelerated schedules
| Schedule | Workdays | Calendar days | Man-hours | Overtime hours | Labor cost |
|---|---|---|---|---|---|
| Regular | 4 | 4 | 120 hr | 0 hr | $5,400.00 |
| Accelerated | 4 | 4 | 138 hr | 18 hr | $6,615.00 |
How to use this example
Use total efficiency loss as a planning stress test for extra time blocked by work windows or site constraints. Scheduled overtime still incurs pay when it is used.
The regular and accelerated completion dates are the same. Compare the labor cost before committing to extra shifts or hours.
Open calculator defaultsFrequently asked questions
What does 100% overtime efficiency loss represent here?
The entered overtime accrues labor cost and contributes zero modeled output. Use it to stress-test paid time when field progress cannot continue.
Why does the last shift skip scheduled overtime?
The model stops paying crew hours once the work is complete. It incurs overtime on prior full shifts even if the entered efficiency yields no progress.
Concrete layout with no overtime output
- Baseline man-hours
- 120 hr
- Planned man-hours including overtime
- 138 hr
- Overtime man-hours
- 18 hr
- Regular workdays
- 4 days
- Planned elapsed calendar days
- 4 days
- Planned elapsed calendar weeks
- 0.57 wk
- Calendar days saved
- 0 days
- Regular labor cost
- $5,400.00
- Planned labor cost
- $6,615.00
- Labor cost increase
- $1,215.00
- Calendar buffer to target
- 2 days
Worksheet inputs
- Takeoff measurement
- Linear length
- Total takeoff quantity
- 2400 ft
- Production rate basis
- Per man-hour
- Baseline production rate
- 20 ft/man-hr
- Crew size
- 3
- Regular hours per workday
- 10 hr
- Scheduled workdays per week
- 4 days
- Extra overtime per workday
- 2 hr
- Overtime efficiency loss
- 100 %
- Regular hourly labor cost
- 45 $
- Overtime wage multiplier
- 1.5 ×
- Target elapsed calendar days
- 6 days
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.