Drywall hanging overtime trade-off
Compare five-person drywall shifts with two overtime hours and 40% efficiency loss across a 16,800 square-foot takeoff.
Worksheet inputs
Results
Field operations- Baseline man-hours
- 560 hr
- Planned man-hours including overtime
- 608 hr
- Overtime man-hours
- 120 hr
- Regular workdays
- 14 days
- Planned elapsed calendar days
- 17 days
- Planned elapsed calendar weeks
- 2.43 wk
- Calendar days saved
- 1 day
- Regular labor cost
- $20,160.00
- Planned labor cost
- $24,048.00
- Labor cost increase
- $3,888.00
- Calendar buffer to target
- −2 days
- Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.
Regular and accelerated schedules
| Schedule | Workdays | Calendar days | Man-hours | Overtime hours | Labor cost |
|---|---|---|---|---|---|
| Regular | 14 | 18 | 560 hr | 0 hr | $20,160.00 |
| Accelerated | 13 | 17 | 608 hr | 120 hr | $24,048.00 |
How to use this example
The production history is measured in square feet per person-hour. Use a separate finishing pace if the crew mix or takeoff differs.
Compare the calendar-days saved with the modeled labor cost increase. A long day adds premium hours while lower output limits schedule compression.
Open calculator defaultsFrequently asked questions
Should drywall finishing use the same rate as hanging?
Estimate the phases separately when their labor mix, curing or lifts differ. Combine the resulting schedule with its actual overlaps and handoffs.
Can extra hours save fewer days than they add to payroll?
Yes. Some extra hours might be less productive, and the job still requires the same final scheduled shift. Compare overtime hours and the calendar result together.
Drywall hanging overtime trade-off
- Baseline man-hours
- 560 hr
- Planned man-hours including overtime
- 608 hr
- Overtime man-hours
- 120 hr
- Regular workdays
- 14 days
- Planned elapsed calendar days
- 17 days
- Planned elapsed calendar weeks
- 2.43 wk
- Calendar days saved
- 1 day
- Regular labor cost
- $20,160.00
- Planned labor cost
- $24,048.00
- Labor cost increase
- $3,888.00
- Calendar buffer to target
- −2 days
Worksheet inputs
- Takeoff measurement
- Area
- Total takeoff quantity
- 16800 ft²
- Production rate basis
- Per man-hour
- Baseline production rate
- 30 ft²/man-hr
- Crew size
- 5
- Regular hours per workday
- 8 hr
- Scheduled workdays per week
- 5 days
- Extra overtime per workday
- 2 hr
- Overtime efficiency loss
- 40 %
- Regular hourly labor cost
- 36 $
- Overtime wage multiplier
- 1.5 ×
- Target elapsed calendar days
- 15 days
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.