Drywall hanging overtime trade-off

Compare five-person drywall shifts with two overtime hours and 40% efficiency loss across a 16,800 square-foot takeoff.

Worksheet inputs

Scope and baseline production
ft²
ft²/man-hr
hr
days
Overtime, wage and target
hr
%
$
×
days
Use zero to leave the target unset.

Results

Field operations
Workdays on accelerated schedule13 days
Baseline man-hours
560 hr
Planned man-hours including overtime
608 hr
Overtime man-hours
120 hr
Regular workdays
14 days
Planned elapsed calendar days
17 days
Planned elapsed calendar weeks
2.43 wk
Calendar days saved
1 day
Regular labor cost
$20,160.00
Planned labor cost
$24,048.00
Labor cost increase
$3,888.00
Calendar buffer to target
−2 days
Schedule and labor cost at each pace
Schedule and labor cost at each paceElapsed calendar days. Regular 18 days. Accelerated 17 days. Labor cost. Regular $20,160.00. Accelerated $24,048.00Elapsed calendar days18 days17 daysLabor cost$20,160.00$24,048.00RegularAccelerated
  • Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.

Regular and accelerated schedules

ScheduleWorkdaysCalendar daysMan-hoursOvertime hoursLabor cost
Regular1418560 hr0 hr$20,160.00
Accelerated1317608 hr120 hr$24,048.00

How to use this example

The production history is measured in square feet per person-hour. Use a separate finishing pace if the crew mix or takeoff differs.

Compare the calendar-days saved with the modeled labor cost increase. A long day adds premium hours while lower output limits schedule compression.

Open calculator defaults

Frequently asked questions

Should drywall finishing use the same rate as hanging?

Estimate the phases separately when their labor mix, curing or lifts differ. Combine the resulting schedule with its actual overlaps and handoffs.

Can extra hours save fewer days than they add to payroll?

Yes. Some extra hours might be less productive, and the job still requires the same final scheduled shift. Compare overtime hours and the calendar result together.