Firestop penetration count and partial final shift

Plan a two-person firestop crew using observed penetrations per man-hour and a partially used final shift under overtime.

Worksheet inputs

Scope and baseline production
units
units/man-hr
hr
days
Overtime, wage and target
hr
%
$
×
days
Use zero to leave the target unset.

Results

Field operations
Workdays on accelerated schedule3 days
Baseline man-hours
51.25 hr
Planned man-hours including overtime
52.45 hr
Overtime man-hours
6 hr
Regular workdays
4 days
Planned elapsed calendar days
3 days
Planned elapsed calendar weeks
0.43 wk
Calendar days saved
1 day
Regular labor cost
$2,203.75
Planned labor cost
$2,384.35
Labor cost increase
$180.60
Calendar buffer to target
1 day
Schedule and labor cost at each pace
Schedule and labor cost at each paceElapsed calendar days. Regular 4 days. Accelerated 3 days. Labor cost. Regular $2,203.75. Accelerated $2,384.35Elapsed calendar days4 days3 daysLabor cost$2,203.75$2,384.35RegularAccelerated
  • Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.

Regular and accelerated schedules

ScheduleWorkdaysCalendar daysMan-hoursOvertime hoursLabor cost
Regular4451.25 hr0 hr$2,203.75
Accelerated3352.45 hr6 hr$2,384.35

How to use this example

Different wall types and penetrations can have materially different production. Use the average rate for a group whose methods reflect the takeoff.

Check the man-hours and the target buffer together. The model counts only the working time needed on the final scheduled shift.

Open calculator defaults

Frequently asked questions

How do I price firestop work that varies by diameter?

Separate typical penetrations from larger or complex systems. Estimate each quantity with a rate from comparable work and add their man-hours.

Do final inspection hours belong in the installation rate?

Add them to the observed scope rate when the same crew performs the inspection work. Use a separate task for external inspections and waits.