Firestop penetration count and partial final shift
Plan a two-person firestop crew using observed penetrations per man-hour and a partially used final shift under overtime.
Worksheet inputs
Results
Field operations- Baseline man-hours
- 51.25 hr
- Planned man-hours including overtime
- 52.45 hr
- Overtime man-hours
- 6 hr
- Regular workdays
- 4 days
- Planned elapsed calendar days
- 3 days
- Planned elapsed calendar weeks
- 0.43 wk
- Calendar days saved
- 1 day
- Regular labor cost
- $2,203.75
- Planned labor cost
- $2,384.35
- Labor cost increase
- $180.60
- Calendar buffer to target
- 1 day
- Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.
Regular and accelerated schedules
| Schedule | Workdays | Calendar days | Man-hours | Overtime hours | Labor cost |
|---|---|---|---|---|---|
| Regular | 4 | 4 | 51.25 hr | 0 hr | $2,203.75 |
| Accelerated | 3 | 3 | 52.45 hr | 6 hr | $2,384.35 |
How to use this example
Different wall types and penetrations can have materially different production. Use the average rate for a group whose methods reflect the takeoff.
Check the man-hours and the target buffer together. The model counts only the working time needed on the final scheduled shift.
Open calculator defaultsFrequently asked questions
How do I price firestop work that varies by diameter?
Separate typical penetrations from larger or complex systems. Estimate each quantity with a rate from comparable work and add their man-hours.
Do final inspection hours belong in the installation rate?
Add them to the observed scope rate when the same crew performs the inspection work. Use a separate task for external inspections and waits.
Firestop penetration count and partial final shift
- Baseline man-hours
- 51.25 hr
- Planned man-hours including overtime
- 52.45 hr
- Overtime man-hours
- 6 hr
- Regular workdays
- 4 days
- Planned elapsed calendar days
- 3 days
- Planned elapsed calendar weeks
- 0.43 wk
- Calendar days saved
- 1 day
- Regular labor cost
- $2,203.75
- Planned labor cost
- $2,384.35
- Labor cost increase
- $180.60
- Calendar buffer to target
- 1 day
Worksheet inputs
- Takeoff measurement
- Counted items
- Total takeoff quantity
- 205 units
- Production rate basis
- Per man-hour
- Baseline production rate
- 4 units/man-hr
- Crew size
- 2
- Regular hours per workday
- 8 hr
- Scheduled workdays per week
- 5 days
- Extra overtime per workday
- 1.5 hr
- Overtime efficiency loss
- 20 %
- Regular hourly labor cost
- 43 $
- Overtime wage multiplier
- 1.5 ×
- Target elapsed calendar days
- 4 days
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.