Commercial roofing schedule in square metres

Use a crew-day roofing rate and metric display to compare six-day weeks with reduced-productivity overtime on a commercial roof.

Worksheet inputs

Scope and baseline production
m²
m²/crew-day
hr
days
Overtime, wage and target
hr
%
C$
×
days
Use zero to leave the target unset.

Results

Field operations
Workdays on accelerated schedule10 days
Baseline man-hours
648 hr
Planned man-hours including overtime
680.4 hr
Overtime man-hours
162 hr
Regular workdays
12 days
Planned elapsed calendar days
11 days
Planned elapsed calendar weeks
1.57 wk
Calendar days saved
2 days
Regular labor cost
C$25,272.00
Planned labor cost
C$29,694.60
Labor cost increase
C$4,422.60
Calendar buffer to target
1 day
Schedule and labor cost at each pace
Schedule and labor cost at each paceElapsed calendar days. Regular 13 days. Accelerated 11 days. Labor cost. Regular C$25,272.00. Accelerated C$29,694.60Elapsed calendar days13 days11 daysLabor costC$25,272.00C$29,694.60RegularAccelerated
  • Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.

Regular and accelerated schedules

ScheduleWorkdaysCalendar daysMan-hoursOvertime hoursLabor cost
Regular1213648 hr0 hrC$25,272.00
Accelerated1011680.4 hr162 hrC$29,694.60

How to use this example

The takeoff and rate show square metres in the editor. The same crew can be viewed in square feet without changing the job duration.

Allow for hoist availability and weather exposure in the production sample. Use separate planning for stoppages that the sample excludes.

Open calculator defaults

Frequently asked questions

Can a larger roofing crew use the same crew-day output?

Update the observed crew-day rate with the new staffing assumption. Site access, hoisting and work fronts can prevent output from scaling linearly.

How should I represent time waiting for a crane?

Use a historical rate that includes normal wait time or schedule the wait explicitly. Avoid charging both effects for the same interruption.