Commercial roofing schedule in square metres
Use a crew-day roofing rate and metric display to compare six-day weeks with reduced-productivity overtime on a commercial roof.
Worksheet inputs
Results
Field operations- Baseline man-hours
- 648 hr
- Planned man-hours including overtime
- 680.4 hr
- Overtime man-hours
- 162 hr
- Regular workdays
- 12 days
- Planned elapsed calendar days
- 11 days
- Planned elapsed calendar weeks
- 1.57 wk
- Calendar days saved
- 2 days
- Regular labor cost
- C$25,272.00
- Planned labor cost
- C$29,694.60
- Labor cost increase
- C$4,422.60
- Calendar buffer to target
- 1 day
- Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.
Regular and accelerated schedules
| Schedule | Workdays | Calendar days | Man-hours | Overtime hours | Labor cost |
|---|---|---|---|---|---|
| Regular | 12 | 13 | 648 hr | 0 hr | C$25,272.00 |
| Accelerated | 10 | 11 | 680.4 hr | 162 hr | C$29,694.60 |
How to use this example
The takeoff and rate show square metres in the editor. The same crew can be viewed in square feet without changing the job duration.
Allow for hoist availability and weather exposure in the production sample. Use separate planning for stoppages that the sample excludes.
Open calculator defaultsFrequently asked questions
Can a larger roofing crew use the same crew-day output?
Update the observed crew-day rate with the new staffing assumption. Site access, hoisting and work fronts can prevent output from scaling linearly.
How should I represent time waiting for a crane?
Use a historical rate that includes normal wait time or schedule the wait explicitly. Avoid charging both effects for the same interruption.
Commercial roofing schedule in square metres
- Baseline man-hours
- 648 hr
- Planned man-hours including overtime
- 680.4 hr
- Overtime man-hours
- 162 hr
- Regular workdays
- 12 days
- Planned elapsed calendar days
- 11 days
- Planned elapsed calendar weeks
- 1.57 wk
- Calendar days saved
- 2 days
- Regular labor cost
- C$25,272.00
- Planned labor cost
- C$29,694.60
- Labor cost increase
- C$4,422.60
- Calendar buffer to target
- 1 day
Worksheet inputs
- Takeoff measurement
- Area
- Total takeoff quantity
- 1003.352832 m²
- Production rate basis
- Per crew-day
- Baseline production rate
- 83.612736 m²/crew-day
- Crew size
- 6
- Regular hours per workday
- 9 hr
- Scheduled workdays per week
- 6 days
- Extra overtime per workday
- 3 hr
- Overtime efficiency loss
- 20 %
- Regular hourly labor cost
- 39 C$
- Overtime wage multiplier
- 1.5 ×
- Target elapsed calendar days
- 12 days
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.