Storefront fixture installs and weekend timing
Estimate fixture count, crew man-hours and elapsed duration when overtime still leaves the final work on the next scheduled shift.
Worksheet inputs
Results
Field operations- Baseline man-hours
- 192 hr
- Planned man-hours including overtime
- 202 hr
- Overtime man-hours
- 40 hr
- Regular workdays
- 6 days
- Planned elapsed calendar days
- 8 days
- Planned elapsed calendar weeks
- 1.14 wk
- Calendar days saved
- 0 days
- Regular labor cost
- $6,720.00
- Planned labor cost
- $7,770.00
- Labor cost increase
- $1,050.00
- Calendar buffer to target
- −2 days
- Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.
Regular and accelerated schedules
| Schedule | Workdays | Calendar days | Man-hours | Overtime hours | Labor cost |
|---|---|---|---|---|---|
| Regular | 6 | 8 | 192 hr | 0 hr | $6,720.00 |
| Accelerated | 6 | 8 | 202 hr | 40 hr | $7,770.00 |
How to use this example
The rate represents repetitive fixtures with materials staged. Pull setup and site protection into their own tasks if they are outside the measured sample.
The target is elapsed calendar days. Compare the counted sixth workday with the days off before it in a five-day schedule.
Open calculator defaultsFrequently asked questions
What if a store allows fewer hours per night than the regular shift?
Enter the actual access window as regular hours. Use the observed night-shift pace and only include permitted overtime.
Does switching to Metric alter a fixture count?
Counts use the same units in both systems. The selector converts area and length, while the number of fixtures stays unchanged.
Storefront fixture installs and weekend timing
- Baseline man-hours
- 192 hr
- Planned man-hours including overtime
- 202 hr
- Overtime man-hours
- 40 hr
- Regular workdays
- 6 days
- Planned elapsed calendar days
- 8 days
- Planned elapsed calendar weeks
- 1.14 wk
- Calendar days saved
- 0 days
- Regular labor cost
- $6,720.00
- Planned labor cost
- $7,770.00
- Labor cost increase
- $1,050.00
- Calendar buffer to target
- −2 days
Worksheet inputs
- Takeoff measurement
- Counted items
- Total takeoff quantity
- 480 units
- Production rate basis
- Per man-hour
- Baseline production rate
- 2.5 units/man-hr
- Crew size
- 4
- Regular hours per workday
- 8 hr
- Scheduled workdays per week
- 5 days
- Extra overtime per workday
- 2 hr
- Overtime efficiency loss
- 25 %
- Regular hourly labor cost
- 35 $
- Overtime wage multiplier
- 1.5 ×
- Target elapsed calendar days
- 6 days
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.