Storefront fixture installs and weekend timing

Estimate fixture count, crew man-hours and elapsed duration when overtime still leaves the final work on the next scheduled shift.

Worksheet inputs

Scope and baseline production
units
units/man-hr
hr
days
Overtime, wage and target
hr
%
$
×
days
Use zero to leave the target unset.

Results

Field operations
Workdays on accelerated schedule6 days
Baseline man-hours
192 hr
Planned man-hours including overtime
202 hr
Overtime man-hours
40 hr
Regular workdays
6 days
Planned elapsed calendar days
8 days
Planned elapsed calendar weeks
1.14 wk
Calendar days saved
0 days
Regular labor cost
$6,720.00
Planned labor cost
$7,770.00
Labor cost increase
$1,050.00
Calendar buffer to target
−2 days
Schedule and labor cost at each pace
Schedule and labor cost at each paceElapsed calendar days. Regular 8 days. Accelerated 8 days. Labor cost. Regular $6,720.00. Accelerated $7,770.00Elapsed calendar days8 days8 daysLabor cost$6,720.00$7,770.00RegularAccelerated
  • Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.

Regular and accelerated schedules

ScheduleWorkdaysCalendar daysMan-hoursOvertime hoursLabor cost
Regular68192 hr0 hr$6,720.00
Accelerated68202 hr40 hr$7,770.00

How to use this example

The rate represents repetitive fixtures with materials staged. Pull setup and site protection into their own tasks if they are outside the measured sample.

The target is elapsed calendar days. Compare the counted sixth workday with the days off before it in a five-day schedule.

Open calculator defaults

Frequently asked questions

What if a store allows fewer hours per night than the regular shift?

Enter the actual access window as regular hours. Use the observed night-shift pace and only include permitted overtime.

Does switching to Metric alter a fixture count?

Counts use the same units in both systems. The selector converts area and length, while the number of fixtures stays unchanged.