Underground conduit output per crew-day
Convert a measured whole-crew conduit production rate into person-hours, scheduled shifts and calendar duration on a six-day workweek.
Worksheet inputs
Results
Field operations- Baseline man-hours
- 360 hr
- Planned man-hours including overtime
- 360 hr
- Overtime man-hours
- 0 hr
- Regular workdays
- 15 days
- Planned elapsed calendar days
- 17 days
- Planned elapsed calendar weeks
- 2.43 wk
- Calendar days saved
- 0 days
- Regular labor cost
- $15,120.00
- Planned labor cost
- $15,120.00
- Labor cost increase
- $0.00
- Calendar buffer to target
- 3 days
- Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.
Regular and accelerated schedules
| Schedule | Workdays | Calendar days | Man-hours | Overtime hours | Labor cost |
|---|---|---|---|---|---|
| Regular | 15 | 17 | 360 hr | 0 hr | $15,120.00 |
| Accelerated | 15 | 17 | 360 hr | 0 hr | $15,120.00 |
How to use this example
Historical output is 160 feet per complete eight-hour shift for the three-person crew. Leave the crew size unchanged when applying this specific rate.
Count inspection or backfill stoppages in the historical production basis or model them as separate schedule constraints.
Open calculator defaultsFrequently asked questions
Can I switch from feet to metres without changing the estimated shifts?
Yes. The unit selector converts both trench quantity and the entered production rate. The crew and shift basis stay the same.
How do utility crossings affect conduit production?
Use a lower observed rate where crossings dominate, or separate the crossings into their own scoped estimate with appropriate setup and inspection.
Underground conduit output per crew-day
- Baseline man-hours
- 360 hr
- Planned man-hours including overtime
- 360 hr
- Overtime man-hours
- 0 hr
- Regular workdays
- 15 days
- Planned elapsed calendar days
- 17 days
- Planned elapsed calendar weeks
- 2.43 wk
- Calendar days saved
- 0 days
- Regular labor cost
- $15,120.00
- Planned labor cost
- $15,120.00
- Labor cost increase
- $0.00
- Calendar buffer to target
- 3 days
Worksheet inputs
- Takeoff measurement
- Linear length
- Total takeoff quantity
- 2400 ft
- Production rate basis
- Per crew-day
- Baseline production rate
- 160 ft/crew-day
- Crew size
- 3
- Regular hours per workday
- 8 hr
- Scheduled workdays per week
- 6 days
- Extra overtime per workday
- 0 hr
- Overtime efficiency loss
- 0 %
- Regular hourly labor cost
- 42 $
- Overtime wage multiplier
- 1.5 ×
- Target elapsed calendar days
- 20 days
Use these deterministic job-costing and financial-planning models with your own rates. Legal contract language, AIA forms advice, tax advice, and binding bid guarantees are outside their scope. Confirm local retainage statutes, prevailing-wage rules, bond and insurance rates, and signed subcontract terms before bidding.