Underground conduit output per crew-day

Convert a measured whole-crew conduit production rate into person-hours, scheduled shifts and calendar duration on a six-day workweek.

Worksheet inputs

Scope and baseline production
ft
ft/crew-day
hr
days
Overtime, wage and target
hr
%
$
×
days
Use zero to leave the target unset.

Results

Field operations
Workdays on regular schedule15 days
Baseline man-hours
360 hr
Planned man-hours including overtime
360 hr
Overtime man-hours
0 hr
Regular workdays
15 days
Planned elapsed calendar days
17 days
Planned elapsed calendar weeks
2.43 wk
Calendar days saved
0 days
Regular labor cost
$15,120.00
Planned labor cost
$15,120.00
Labor cost increase
$0.00
Calendar buffer to target
3 days
Schedule and labor cost at each pace
Schedule and labor cost at each paceElapsed calendar days. Regular 17 days. Accelerated 17 days. Labor cost. Regular $15,120.00. Accelerated $15,120.00Elapsed calendar days17 days17 daysLabor cost$15,120.00$15,120.00RegularAccelerated
  • Overtime hours contribute at the entered reduced pace and earn the entered wage multiplier. The last shift stops when the scope is complete. Calendar days start on the first scheduled workday and include intervening days off.

Regular and accelerated schedules

ScheduleWorkdaysCalendar daysMan-hoursOvertime hoursLabor cost
Regular1517360 hr0 hr$15,120.00
Accelerated1517360 hr0 hr$15,120.00

How to use this example

Historical output is 160 feet per complete eight-hour shift for the three-person crew. Leave the crew size unchanged when applying this specific rate.

Count inspection or backfill stoppages in the historical production basis or model them as separate schedule constraints.

Open calculator defaults

Frequently asked questions

Can I switch from feet to metres without changing the estimated shifts?

Yes. The unit selector converts both trench quantity and the entered production rate. The crew and shift basis stay the same.

How do utility crossings affect conduit production?

Use a lower observed rate where crossings dominate, or separate the crossings into their own scoped estimate with appropriate setup and inspection.