Boom crane sale before financing maturity

Compare crane rentals with a financed purchase sold at year five even though the original equipment loan extends to year seven.

Worksheet inputs

Ownership and useful life
$
%
yr
yr
%
$
$
$
Rental quotes and planned use

Enter zero for unavailable quotes. Billing blocks are prorated using your entered days per rental period.

$
$
$
days
days
$
days

Results

Field operations
Break-even utilization per year31.12 days
Annual cost verdict
Buy at this utilization
Annual ownership cost
$79,558.42
Annual rental at planned use
$111,960.00
Equivalent rental cost per use day
$1,920.00
Annual rental delivery and pickup
$19,800.00
Annual savings from buying
$32,401.58
Five-year net cost of buying
$397,792.10
Five-year net cost of renting
$559,800.00
Monthly loan payment
$4,893.74
Annual cost by utilization days
Annual cost by utilization daysOwnership cost. Rental cost. Break-even, day 31.12, $79,558.42. Planned use, day 48, $111,960.00$0$360.3K$720.6K0183365Use days per yearOwnership costRental costBreak-even · 31.12Planned use · 48
  • Weekly quote drives the crossover. Rental rates are prorated per use day. Annual freight applies once any rental occurs.
  • Financed ownership averages loan outlays less resale across useful life. Five-year totals include loan payoff, replacements at useful life, and straight-line estimated resale at exit.

Rental quote comparison

QuotePer use dayAnnual at planned use
Daily quote$2,600.00$144,600.00
Weekly quote$1,920.00$111,960.00
Monthly quote$1,575.00$95,400.00

How to use this example

The original loan has two years remaining at the planned exit. The calculation pays off the remaining balance when the machine is sold.

Use rent and own quotes with similar capacity and a comparable operator basis. Confirm the actual payoff, inspection and transportation estimates.

Open calculator defaults

Frequently asked questions

Does selling the crane cancel the remaining loan payments?

The model includes a payoff equal to the outstanding balance at sale. Check early payoff fees and lien release with the lender.

Should a crane operator be included in the rental quote?

Compare like-for-like operator costs. Add or separate the operator on each side before entering rates if one quote includes staffing.