Construction Estimating and Job-Costing Methodology

Review the equations, timing rules and cost bases behind the eight construction worksheets.

Markup and margin use different denominators

A 25% markup prices 100 of work at 125, yielding a 20% gross margin. A 25% gross margin prices the same work at 133.33. Enter overhead and desired net profit as shares of the base bid. The model prices bond and tax as pass-throughs on their selected base and excludes them from gross and net margin.

Bid price and margin
Margin = (price − direct cost) ÷ price
Markup = margin ÷ (1 − margin)
Price multiplier = 1 ÷ (1 − margin)

Paid hours and billed hours both shape the rate

Annual direct labor includes wages, entered payroll burden and annual field support costs. Company overhead adds to direct cost per billable hour. Divide break-even by one minus the target net margin to recover both cost and return from time you invoice.

Crew labor billing rate
Loaded cost = annual direct labor cost ÷ paid hours
Billable break-even = loaded cost ÷ utilization × (1 + overhead rate)

One overhead budget, two recovery bases

This dual-rate Multiple Overhead Recovery System (MORS) applies a handling markup to materials and subcontractors. It caps that allocation at annual overhead and assigns the rest to field labor. A rate lower than the blended rate on the materials base shifts more recovery to each field labor dollar and hour.

Overhead recovery
Single rate = fixed overhead ÷ total direct costs
Field labor recovery = fixed overhead − materials recovery

SOV progress, stored materials and retainage

AIA G702 and G703 organize payment applications around the contract sum, earned value, retainage and prior certificates. This planner uses value-weighted installed work to trigger an optional step-down, set to 50% by default. The excess-only setting retains the original rate on the first cumulative value tranche. The re-rate setting applies the reduced rate across cumulative eligible value.

Progress billing and retainage
Cumulative eligible value = installed to date + eligible stored materials
Current draw = cumulative eligible value − retainage − prior certificates

Apply each change order fee to its own base

The subcontract quote has its own markup and overhead allocation. Extended general conditions are the daily cost times added days. The model applies the bond and insurance adder last to the signed subtotal. Check the signed agreement for the permitted bases and fee caps.

Change order pricing
Stacked self-performed factor = (1 + overhead rate) × (1 + profit rate)
Additive factor = 1 + overhead rate + profit rate

Ownership and rental cross at a use threshold

Ownership includes recovery of capital after salvage, upkeep, insurance and storage. Cash mode uses an annualized opportunity cost. Finance mode uses monthly amortization and includes an exit payoff when needed. When any equipment is rented, job-level delivery and pickup add to prorated use. The five-year view models resale and replacement within the horizon.

Equipment buy vs. rent
Crossover days = (annual ownership − job freight) ÷ prorated daily rental

Overtime adds paid time and less productive time

Convert the takeoff rate to output per person-hour, then fill each regular shift and its extra hours at the entered pace. The final shift stops at completion. The calendar includes days off between worked shifts and measures the resulting buffer against a target date expressed in elapsed days.

Crew production and schedule
Productive shift capacity = regular hours + overtime hours × (1 − efficiency loss)
Man-hours = actual crew hours × crew size

Billing lag separates earnings from cash

Progress accrues evenly and payments arrive on Net 30, 45 or 60 terms. The model tracks payroll and supplier disbursements separately and credits mobilization proportionally. It solves the smallest deposit that keeps every projected funding point nonnegative, subject to retainage and the payable contract value.

Working capital and payment terms
Receipt day = billing day + terms in calendar days
Peak funding = magnitude of the lowest negative cash point

Frequently asked questions

What does the model count as direct cost?

Direct cost follows the job. It can include installed material, field wages and burden, subcontract work and job equipment. Company expenses belong in overhead unless the specific job incurs them.

Does currency selection apply an exchange rate?

Currency selection changes the display symbol and export label. Enter all costs and rates in the same currency or convert them before using a sheet.

How do I compare options with different timing?

Use the same assumptions and horizon for each option. In the cash flow tool, change billing cadence and terms individually to see which payment event moves the funding trough.

When is a projected margin useful for risk review?

Use it to test how much direct cost or overhead can change before the target return is missed. Review exclusions and uncertainty in quantities separately before signing a bid.