4 × 8 Drywall and Level 4 Compound for a 12 × 16 Room

Calculate 4 × 8 board count, Level 4 joint compound, tape, and screws for 8-foot walls with one door.

Project inputs

Board area
ft
ft
ft
ft²
Joint treatment
%
gal/1,000 ft²Leave at 0 for the finish-level planning rate.
US gal
ft/ft²
ft
Bead and screws
ft
screws/ft²
View shopping list

Shopping list

15 sheetsDrywall 4 ft × 8 ft

  • Joint compoundLevel 4 · 4.5 US gal each
    1 bucket
  • Paper joint tape250 ft each
    1 roll
  • Corner bead10 ft each
    0 sticks
  • Drywall screws500 screws each
    2 boxes
Net board area
427 ft²
Compound needed
4.27 US gal
Tape length
157.99 ft
Screws needed
513

Wall sheet layout Wall sheet layout 16 ft 8 ft 4 ft × 8 ft boards · Level 4 finish
Schematic layout

Worked takeoff

  1. Calculate board coverage

    448 ft² walls − 21 ft² openings + 0 ft² ceiling = 427 ft². With 10% cut allowance, plan for 469.7 ft².

  2. Round up the sheets

    469.7 ft² ÷ 32 ft² per sheet rounds up to 15.

  3. Budget Level 4 compound

    427 ft² at 10 gal/1,000 ft² = 4.27 US gal and 1 whole buckets.

  4. Estimate tape, bead, and screws

    157.99 ft tape gives 1 rolls. 0 ft of outside corners gives 0 sticks, rounded per corner. 513 screws gives 2 boxes.

Check before you buy

Confirm board orientation and remove the doorway deduction if the sheet layout consumes a full panel across it. Use the manufacturer’s fastener schedule and compound yield.

Sketch actual sheet joints before buying. Verify board orientation, screw spacing, tape compatibility, and compound yield for the specified assembly and finish.

Frequently asked questions

Why does a 12 × 16 room take 15 sheets after a doorway deduction?

After the 21 ft² door, the net board coverage is 427 ft². The 10% cut allowance increases it to 469.7 ft², a little under 15 whole sheets.

Is one 500-count screw box enough for this Level 4 example?

The planning screw rate gives 513 screws for the net board area, so the current settings estimate two 500-count boxes.