Worked example · VFX & finishing
When startup dominates a short render farm job
A studio tests sending 480 simple graphics frames to a farm. They measure five seconds per frame and about 30 minutes to stage the job either way.
Results
- Farm ETA
- 35 min
- Estimated compute cost
- $4.20 USD
- One-worker ETA
- 1 h 10 min
- Effective speedup
- 2 ×
- Billed node-hours
- 4.667 h
- Busy node-hours
- 0.667 h
- Throughput
- 822.857 frames/h
- Frames in job
- 480 frames
8 active workers · 60 batches.
Input settings
- Specify the sequence by
- Total frames
- Total frames
- 480
- Measured time per frame
- 5
- Per-frame time unit
- Seconds
- Available worker nodes
- 8
- Fixed job overhead (min)
- 30
- Price per node-hour (USD)
- 0.9
Try a change
Reduce the fixed overhead to five minutes, representing cached scene assets. Compare elapsed speedup and billed time.
Questions
Why are eight workers only twice as fast in this graphics job?
The worker pool cuts the frame processing portion to five minutes while the fixed startup remains 30 minutes.
What should I measure first if short farm jobs are slow?
Log startup, data staging and frame processing separately. Reducing shared setup time can help more than adding workers.