Zone B offset = 0.04125253 − (0.08052493) = -0.0392724 m³/s.
Starting result snapshot
A–B step
+17 Pa
B–C step
+17 Pa
Zone A offset
+289.89 m³/h
Zone C offset
-148.509 m³/h
Equations and assumptions
Door-crack and other paths
A = perimeter × gap + A_other
Include only the portion of perimeter with a leak path. Enter wall, pass-through and fitting leakage as equivalent area at the same discharge coefficient.
Use Pa, m² and kg/m³ for Q in m³/s. All three pressures share the same reference. The differential across each closed barrier determines both rate and direction.
Supply minus exhaust
A: Q_AB · B: Q_BC − Q_AB · C: −Q_BC
These are the room offsets attributable to the two modeled door links. Add other envelope paths and use a balanced airflow network for the full system. Open doors, transients and alarm tolerances require testing.
Ladder check
Minimum aligned step = min(s × ΔP_AB, s × ΔP_BC)
The sign s is +1 for an A-to-C cascade and −1 for containment toward A. The FDA closed-door aseptic guidance gives 10–15 Pa as a typical example between different clean classifications. Use the project pressure specification.
Both pressure steps meet the entered magnitude and direction.
For preliminary engineering and EHS / Industrial Hygiene review. Design calculations do not replace review by a licensed professional engineer (PE) and a certified industrial hygienist (CIH), commissioning tests, ISO 14644 classification or certification, or assessment against the applicable NFPA 86 edition.