Diesel Budget for Heavy Disk Tillage

Model a 24-foot disk at 5.2 mph and 85% efficiency, then compare diesel cost on 122 acres with a high PTO load.

Effective field capacity 12.86 ac/h
All results

Worksheet inputs

Pass details
65–90% is a starting range for many operations. Use your field records.
Tractor & diesel

Planning estimate

Effective field capacity
12.86 ac/h
Theoretical field capacity
15.13 ac/h
Total time in field
9.49 h
Ideal pass time at full utilization
8.06 h
Time allowed for field losses
1.42 h
Estimated fuel burn per hour
12.3 gal/h
Estimated fuel burn per area
0.956 gal/ac
Estimated diesel for this pass
116.66 US gal
Estimated fuel cost per area
$3.87 per ac
Estimated total fuel cost
$472.49
Capacity kept & time lost
Capacity kept & time lostField capacity12.86 ac/h effective15.13 ac/h theoreticalTime in field9.49 h totalIdeal productive timeField losses

Field note

Rated PTO power is the tractor rating. Enter the assumed equivalent share demanded by the operation and use measured fuel data where available.

Questions from the field

Why is PTO load still used for a drawbar implement?

The fuel estimate uses load expressed as equivalent PTO power. Use a measured or defensible equivalent for the pull required.

Should I lower field efficiency for slower passes on a hill?

Use typical productive-pass speed for slope-related speed changes. Apply efficiency to time or width losses that remain unaccounted for.