NEC Chapter 9 Table 1 uses 53% for one cable, 31% for two and 40% for three or more when that table applies. The diagram shows equivalent area. Installation clearances and jamming depend on the actual cable geometry.
Static and loaded bends
Rstatic = 10 × OD; Rloaded = 20 × OD
These are editable planning multipliers. Compare the planned bend with the cable manufacturer’s loaded minimum and use the actual measured bore for fill.
Capstan pull model
Tout = Tin × e^(μθ) + μ × W × L
Enter the bend angle in degrees. The model uses radians, total bundle weight per length W, and a horizontal straight section after the bend. Sidewall loading at the bend exit is a simple tension/radius estimate.
EMT uses nominal planning bores. The Schedule 40 PVC presets use minimum electrical-conduit bores from the linked CANTEX drawing. HDPE uses IPS SDR 13.5 geometry before wall tolerances. Enter the actual product bore and verify the locally adopted code. The initial 600 lbf threshold is about 2,669 N. Some cable sheets specify 2,700 N separately. Enter the actual cable or pulling assembly rating and plan complex or inclined pulls section by section.
Within entered limits. The entered fill, loaded bend radius and tension screens pass.
Inputs
Conduit type
EMT
Nominal trade size
1-1/4 in.
Measured conduit ID
35.052 mm
Cable outside diameter
8 mm
Identical cables
3
Actual bend radius
250 mm
Bend angle
90 °
Straight length after bend
85 m
Weight per cable length
0.6 N/m
Friction coefficient
0.32 μ
Tension entering bend
120 N
Rated pull tension
2,668.93297 N
Static radius / cable OD
10 ×
Loaded radius / cable OD
20 ×
Results
Internal conduit area
964.974 mm²
Total cable area
150.796 mm²
Calculated fill
15.627 %
NEC fill limit
40 %
Minimum static bend radius
80 mm
Minimum loaded bend radius
160 mm
Tension exiting bend
198.372 N
Straight-run contribution
48.96 N
Total pull tension
247.332 N
Rated tension remaining
2,421.6 N
Estimated sidewall load
793.49 N/m
Follow IEC 60825-2 and ANSI Z136.2 procedures. Never inspect an energized fiber or connector with your eye or an optical magnifier. Verify the installed link with a calibrated power meter and field OTDR at the relevant wavelengths, using appropriate launch and receive fibers and a safe test setup.
Correct the inputs to print an engineering report.