One cable in ½ in. PVC

Confirm the single-cable fill rule on a compact bore with a 10 mm cable.

Inputs

Choose the raceway and size, then enter the measured bore and cable outside diameter. Open Bend and pull to enter the planned route details.

Conduit and cable bundle
mm
mm
Bend and pull
mm
°
m
N/m
μ
N
N
Cable minimum bend factors
×
×
LIVE ANATOMY

Conduit cross-section and pull profile

Conduit cross-section and pull profileCONDUIT FILL46.396%LOADED BEND200mmPULL TENSION157.552NPULL ROOM2.5e+3NAREA EQUIVALENTPULL PROFILE1 cable · 46.4%Bore 14.68 mmBend 45°Out 157.55 NINSTALLATION LIMIT USE0%100% limit87.5% used
Within entered limitsThe entered fill, loaded bend radius and tension screens pass.

Conduit and bends

Internal conduit area
169.283 mm²
Total cable area
78.54 mm²
Calculated fill
46.396 %
NEC fill limit
53 %
Minimum static bend radius
100 mm
Minimum loaded bend radius
200 mm

Pull profile

Tension exiting bend
154.288 N
Straight-run contribution
3.264 N
Total pull tension
157.552 N
Rated tension remaining
2,511.381 N
Estimated sidewall load
670.816 N/m

What to check

A single cable uses the 53% area limit when the table applies.

Open the general conduit fill & pull tension calculator

Formulas and assumptions

Conduit area and NEC fill

Fill (%) = 100 × count × (cable OD / conduit ID)²

NEC Chapter 9 Table 1 uses 53% for one cable, 31% for two and 40% for three or more when that table applies. The diagram shows equivalent area. Installation clearances and jamming depend on the actual cable geometry.

Static and loaded bends

Rstatic = 10 × OD; Rloaded = 20 × OD

These are editable planning multipliers. Compare the planned bend with the cable manufacturer’s loaded minimum and use the actual measured bore for fill.

Capstan pull model

Tout = Tin × e^(μθ) + μ × W × L

Enter the bend angle in degrees. The model uses radians, total bundle weight per length W, and a horizontal straight section after the bend. Sidewall loading at the bend exit is a simple tension/radius estimate.

EMT uses nominal planning bores. The Schedule 40 PVC presets use minimum electrical-conduit bores from the linked CANTEX drawing. HDPE uses IPS SDR 13.5 geometry before wall tolerances. Enter the actual product bore and verify the locally adopted code. The initial 600 lbf threshold is about 2,669 N. Some cable sheets specify 2,700 N separately. Enter the actual cable or pulling assembly rating and plan complex or inclined pulls section by section.

Worked examples

Open a scenario and edit any parameter.