Perfect closure of a 120 by 80 m rectangle
Verify exact cardinal closure and the area of a four-course rectangle.
More examplesSurvey anatomy
Raw & balanced traverse
Computed results
Within target
Measured closure
- Measured length
- 400m
- Σ Latitude ΔN
- 0m
- Σ Departure ΔE
- 0m
- Linear misclosure
- 0m
- Relative precision
- Exact closure
- Project closure limit
- 0.08m
Balanced enclosure
- Adjusted ΣΔN
- 0m
- Adjusted ΣΔE
- 0m
- Adjusted area
- 9,600m²
- Square feet
- 103,333.54ft²
- Acres
- 2.37221ac
- Hectares
- 0.96ha
Measured courses
| Leg | Azimuth° | Lengthm | ΔNm | ΔEm |
|---|---|---|---|---|
| 1 | 90 | 120 | 0 | 120 |
| 2 | 0 | 80 | 80 | 0 |
| 3 | 270 | 120 | 0 | −120 |
| 4 | 180 | 80 | −80 | 0 |
Bowditch adjustments
| Leg | cNm | cEm | Adj. ΔNm | Adj. ΔEm | Adj. Nm | Adj. Em |
|---|---|---|---|---|---|---|
| 1 | 0 | 0 | 0 | 120 | 1,200 | 970 |
| 2 | 0 | 0 | 80 | 0 | 1,280 | 970 |
| 3 | 0 | 0 | 0 | −120 | 1,280 | 850 |
| 4 | 0 | 0 | −80 | −0 | 1,200 | 850 |
Worked check
The opposing distances cancel. The loop is 400 m long, its measured endpoint is at the start, and the adjusted enclosure is 120 × 80 m².
- Measured misclosure (m)
- 0
- Measured length (m)
- 400
- Balanced area (m²)
- 9,600
These checks describe the original example. Reset restores the original inputs.
Formulas and conventions
Compute measured closure
ΔNᵢ = dᵢ cos(αᵢ) · ΔEᵢ = dᵢ sin(αᵢ) · e = √((ΣΔN)² + (ΣΔE)²)
Use oriented azimuths or quadrant bearings and horizontal distances around the entire loop. Relative precision is 1 : (total length ÷ e). An exactly closed loop has zero misclosure and no finite precision denominator.
Balance by the compass rule
cNᵢ = −ΣΔN × dᵢ ÷ Σd · cEᵢ = −ΣΔE × dᵢ ÷ Σd
Corrections are proportional to course length. The adjusted leg components sum to zero, with any binary rounding remainder absorbed on the closing course. Inspect angular closure and blunders before using the adjustment.
Check against a project target
Closure limit = Σd ÷ target denominator
The selected precision target applies to the measured closure. Area comes from the adjusted polygon in local coordinates. Crossed, overlapping, or degenerate adjusted boundaries cannot produce an enclosed parcel area.
More worked examples
Open a case to edit its inputs and compare the original checks.
- One-meter departure misclosure
Distribute the east-west error when one rectangular course is short.
- Three-course right triangle
Close a right triangle with a measured southwest diagonal.
- Six-course L-shaped enclosure
Track the balanced area around a concave, orthogonal outline.
- Legacy survey-foot rectangle
Calculate an enclosure stated in U.S. survey feet, including its area in the working units.
- A 0.3 m east and 0.4 m south error
Combine two measured component errors into a linear closure and test a 1:5,000 goal.
- Five-course loop with a diagonal close
Balance an oblique fifth course against a control loop with cardinal observations.
GeoSurveyLab · Field calculation
Perfect closure of a 120 by 80 m rectangle
Within target
Field inputs
- Working unit
- Meters (m)
- Start northing
- 1200 m
- Start easting
- 850 m
- Number of legs
- 4
- Target precision 1 : N
- 5000
- Measured courses 1
- E / 120
- Measured courses 2
- N / 80
- Measured courses 3
- W / 120
- Measured courses 4
- S / 80
Measured closure
- Measured length
- 400m
- Σ Latitude ΔN
- 0m
- Σ Departure ΔE
- 0m
- Linear misclosure
- 0m
- Relative precision
- Exact closure
- Project closure limit
- 0.08m
Balanced enclosure
- Adjusted ΣΔN
- 0m
- Adjusted ΣΔE
- 0m
- Adjusted area
- 9,600m²
- Square feet
- 103,333.54ft²
- Acres
- 2.3722ac
- Hectares
- 0.96ha
Bowditch adjustments
| Leg | cNm | cEm | Adj. ΔNm | Adj. ΔEm | Adj. Nm | Adj. Em |
|---|---|---|---|---|---|---|
| 1 | 0 | 0 | 0 | 120 | 1,200 | 970 |
| 2 | 0 | 0 | 80 | 0 | 1,280 | 970 |
| 3 | 0 | 0 | 0 | −120 | 1,280 | 850 |
| 4 | 0 | 0 | −80 | −0 | 1,200 | 850 |
For planning, training, and independent checks. Have a locally licensed Professional Land Surveyor (PLS) verify legal boundaries and survey control. Have a licensed Professional Engineer (PE) verify engineering layout and design where required.