Horizontal curve calculator
Lay out a simple circular highway curve from radius or degree and generate exact deflections and subchords.
Worked examplesSurvey anatomy
Circular curve stationing
Computed results
42.5° / 180°
Circular curve elements
- Radius R
- 650ft
- Tangent T
- 252.77118ft
- True arc length
- 482.14721ft
- Long chord LC
- 471.16945ft
- External E
- 47.419ft
- Middle ordinate M
- 44.19488ft
- Reference arc degree
- 8.814735°
- Reference chord degree
- 8.823452°
Control stations
- PC · Curvature
- 15+92.229ft
- PI · Intersection
- 18+45.000ft
- PT · Tangency
- 20+74.376ft
- Station span
- 482.14721ft
- PT deflection from PC
- 21.25°
Deflections and subchords
| Point | Stationft | Arc from PCft | Deflection° | Subchordft | Chord from PCft |
|---|---|---|---|---|---|
| PC | 15+92.229 | 0 | 0 | 0 | 0 |
| Stake | 16+00.000 | 7.77118 | 0.3425 | 7.77113 | 7.77113 |
| Stake | 16+50.000 | 57.77118 | 2.54619 | 49.98767 | 57.75216 |
| Stake | 17+00.000 | 107.77118 | 4.74987 | 49.98767 | 107.64777 |
| Stake | 17+50.000 | 157.77118 | 6.95356 | 49.98767 | 157.38416 |
| Stake | 18+00.000 | 207.77118 | 9.15724 | 49.98767 | 206.88776 |
| Stake | 18+50.000 | 257.77118 | 11.36092 | 49.98767 | 256.08536 |
| Stake | 19+00.000 | 307.77118 | 13.56461 | 49.98767 | 304.90417 |
| Stake | 19+50.000 | 357.77118 | 15.76829 | 49.98767 | 353.272 |
| Stake | 20+00.000 | 407.77118 | 17.97197 | 49.98767 | 401.1173 |
| Stake | 20+50.000 | 457.77118 | 20.17566 | 49.98767 | 448.3693 |
| PT | 20+74.376 | 482.14721 | 21.25 | 24.3746 | 471.16945 |
Formulas and conventions
Choose a degree convention
R = b ÷ Dᵣₐd (arc) · R = b ÷ [2 sin(D ÷ 2)] (chord)
The reference length b is a 100 ft arc or chord by common U.S. convention. It is editable for project-specific bases. True arc stationing is the highway default. Nominal chord stationing uses bΔ ÷ Dchord and reports true arc length separately.
Locate PC, PI and PT
T = R tan(Δ ÷ 2) · Arc = RΔᵣₐd · PC = PI − T · PT = PC + station span
The long chord is 2R sin(Δ ÷ 2). External distance is T tan(Δ ÷ 4). Middle ordinate is R[1 − cos(Δ ÷ 2)]. The field sketch mirrors for left-hand turns.
Stake from the tangent at PC
Deflection = θ ÷ 2 · Subchord = 2R sin[(θᵢ − θᵢ₋₁) ÷ 2]
Place stakes at even station-interval multiples between the two endpoints. Compute θ as the fraction of station span times Δ and use circular geometry for exact straight chords. Left deflection is negative.
Worked examples
Open a case to edit its inputs and compare the original checks.
- A 60° circular highway curve
Find tangent, arc and long chord for a 300 m radius with 60° of intersection.
- A 10° curve by the 100 ft arc
Derive radius and arc length from the customary highway degree definition.
- A 20° curve with nominal chord stationing
Compare nominal 100 ft chord stations with the longer true arc.
- Left-hand curve with signed deflections
Check the sign and magnitude of a left-hand full-curve deflection.
- Short curve between station marks
Generate the PC and PT even when no full stake goes between them.
- 100 ftUS reference chord
Read a legacy degree of curvature measured with a U.S. survey-foot chord.
GeoSurveyLab · Field calculation
Horizontal curve calculator
42.5° / 180°
Field inputs
- Working unit
- International foot (ft)
- Curve input
- Radius
- Intersection angle Δ
- 42.5 °
- Turn
- Right
- Radius
- 650 ft
- Degree reference length
- 100 ft
- PI station
- 18+45.000 ft
- Stake interval
- 50 ft
- Station basis
- True arc length
Circular curve elements
- Radius R
- 650ft
- Tangent T
- 252.7712ft
- True arc length
- 482.1472ft
- Long chord LC
- 471.1694ft
- External E
- 47.419ft
- Middle ordinate M
- 44.1949ft
- Reference arc degree
- 8.8147°
- Reference chord degree
- 8.8235°
Control stations
- PC · Curvature
- 15+92.229ft
- PI · Intersection
- 18+45.000ft
- PT · Tangency
- 20+74.376ft
- Station span
- 482.1472ft
- PT deflection from PC
- 21.25°
Deflections and subchords
| Point | Stationft | Arc from PCft | Deflection° | Subchordft | Chord from PCft |
|---|---|---|---|---|---|
| PC | 15+92.229 | 0 | 0 | 0 | 0 |
| Stake | 16+00.000 | 7.7712 | 0.3425 | 7.7711 | 7.7711 |
| Stake | 16+50.000 | 57.7712 | 2.5462 | 49.9877 | 57.7522 |
| Stake | 17+00.000 | 107.7712 | 4.7499 | 49.9877 | 107.6478 |
| 4 rows omitted. Download CSV for the full table. | |||||
| Stake | 19+50.000 | 357.7712 | 15.7683 | 49.9877 | 353.272 |
| Stake | 20+00.000 | 407.7712 | 17.972 | 49.9877 | 401.1173 |
| Stake | 20+50.000 | 457.7712 | 20.1757 | 49.9877 | 448.3693 |
| PT | 20+74.376 | 482.1472 | 21.25 | 24.3746 | 471.1694 |
For planning, training, and independent checks. Have a locally licensed Professional Land Surveyor (PLS) verify legal boundaries and survey control. Have a licensed Professional Engineer (PE) verify engineering layout and design where required.