Robotics Commissioning Field Guide
Checks to take from the worksheet to the factory floor, from mastering through grip, ramp and vision trials.
Capture the as-built baseline
- Record robot mastering, base frame, tool frame, flange stack-up and the loaded center of gravity.
- Record firmware profile, speed overrides, shaft rating and the worst payload variant.
- Open the worksheet that matches the operation, enter measured values, then export its inputs and results with the setup record.
Check reach and rate along the path
At pickup and place, check both elbow branches against joint stops, tooling and fixture clearance. Sample the path between those poses and through the approach. Watch the Jacobian condition number and compare the inverse joint rates with the controller limits.
A reachable endpoint can still have an obstructed approach. Check any fixed orientations and verify the active branch in the taught path.
Confirm motion and axis loading
Record real stroke, programmed velocity, acceleration and jerk caps. Include index and dwell time in cycle comparison. Compare gear peak torque and motor continuous thermal ratings on the intended duty cycle using logged drive data.
Test the worst grip case
Repeat lift and transfer with representative surface variation, acceleration and stop deceleration. For jaws, measure pad-to-part friction under dry and contaminated conditions. For suction, record vacuum at the cups under flow and account for side loads and failed seals.
Validate the AMR envelope
Compare measured wheel radii and chassis track with odometry. Mark the axle reference and sweep the actual body, load and attachments through the aisle. Check uphill torque at the gross vehicle load, and confirm traction and stopping distance on the installed floor.
Prove the image at depth
Verify the smallest real feature across all four field corners and the acceptable workpiece heights. Lock exposure and lighting, capture representative parts with motion, and check measured repeatability at the intended line rate.
Save the commissioning record
Print the A4 worksheet with the active inputs and verdict. Attach drawings, measured evidence and controller settings. Record where equipment limits, installation tolerances or measured performance govern the final decision.