Chamber pump-down time / Worked example
Wafer Load Lock Cycle Time
A 36 L load lock starts each cycle at atmosphere. A dry scroll pump hands off to high vacuum at 12 Pa without a Roots booster.
Inputs
Roots booster
Walls, seals and leaks
Live readout
Target vacuum met- Roughing time
- 54.25 s
- Backing-only roughing time
- 54.25 s
- Boosted roughing time
- 0 s
- High-vacuum stage
- 4.184 s
- Time to target
- 58.43 s
- Modeled ultimate pressure
- 2.843e-7 Pa
- Wall throughput at target
- 2.349e-6 Pa·m³/s
Reading this example
The roughing time sets the first part of the cycle. The wall load and final decade can dominate the high-vacuum finish.
Model & assumptions
Roughing stages
t = (V/S) ln(Pₐ/Pᵦ)
The backing pump runs above the Roots switch pressure. Use combined speed below the switch, until the high-vacuum pump takes over. Enter chamber-effective speeds for all stages.
High-vacuum mass balance
V dP/dt = A[q∞ + q₁(1 + t/t₁)⁻ᵅ] + Qₗ − SₑP
The high-vacuum clock starts with wall age t₁. The solver integrates the decaying load with exponential chamber memory until pressure crosses the target. At α = 0 the reference wall rate is a steady load.
Ultimate pressure
P∞ = (Aq∞ + Qₗ)/Sₑ (α > 0)
The model rejects a target at or below the ultimate pressure. With a decaying wall load, a target can sit above the floor and still take longer than the 10¹² s search horizon.